OSHA SearchOSHA records by employer

Boniche Structural Corp: OSHA inspections and violations

Miami, Florida · Structural Steel and Precast Concrete Contractors · NAICS 238120

1inspections
10citation items
$27,846current penalties
May 22, 2019last inspection

OSHA has inspected Boniche Structural Corp once in Florida.

The inspection began on May 22, 2019 as part of a related case, in Miami.

That inspection ended with 10 citation items: 10 serious.

Penalties were first proposed at $27,846 and still stand at $27,846.

Power line safety (up to 350 kV)—equipment operations comes up most often in these citations: 6 items under 1926.1408.

How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,079, and Boniche Structural Corp averages $27,846 (1 cited inspection).

Boniche Structural Corp: OSHA citation items per year, 2019 to 2019
Citation items per year, by inspection date.

Want to know if OSHA cites Boniche Structural Corp again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 344050067 OPENED MAY 22, 2019Closed

Unprogrammed related · Partial · Safety · 55 employees at the site · Closed Apr 13, 2023

6320 Sw 8th Street Soleste Alameda 1, Miami, FL 33101 · Structural Steel and Precast Concrete Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1926.1408(a)(2) · Power line safety (up to 350 kV)—equipment operations
Serious$9,282$9,282Oct 18, 2019Final
Citation 1, item 1b
29 CFR 1926.1408(a)(2)(i) · Power line safety (up to 350 kV)—equipment operations
Serious$0$0Oct 18, 2019Final
Citation 1, item 1c
29 CFR 1926.1408(a)(2)(ii) · Power line safety (up to 350 kV)—equipment operations
Serious$0$0Oct 18, 2019Final
Citation 1, item 1d
29 CFR 1926.1408(a)(2)(iii) · Power line safety (up to 350 kV)—equipment operations
Serious$0$0Oct 18, 2019Final
Citation 1, item 1e
29 CFR 1926.1408(d)(1) · Power line safety (up to 350 kV)—equipment operations
Serious$0$0Oct 18, 2019Final
Citation 1, item 2
29 CFR 1926.1408(g)(1)(i) · Power line safety (up to 350 kV)—equipment operations
Serious$9,282$9,282Oct 18, 2019Final
Citation 1, item 3a
29 CFR 1926.1428(a) · Signal person qualifications
Serious$9,282$9,282Oct 18, 2019Final
Citation 1, item 3b
29 CFR 1926.1428(c)(3) · Signal person qualifications
Serious$0$0Oct 18, 2019Final
Citation 1, item 3c
29 CFR 1926.1428(c)(5) · Signal person qualifications
Serious$0$0Oct 18, 2019Final
Citation 1, item 3d Serious$0$0Oct 18, 2019Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.1408 · Power line safety (up to 350 kV)—equipment operations

29 CFR 1926.1408(a)(2)

(2) Determine if any part of the equipment, load line or load (including rigging and lifting accessories), if operated up to the equipment's maximum working radius in the work zone, could get closer than 20 feet to a power line. If so, the employer must meet the requirements in Option (1), Option (2), or Option (3) of this section, as follows:

29 CFR 1926.1408(a)(2)(i)

(i) Option (1)—Deenergize and ground. Confirm from the utility owner/operator that the power line has been deenergized and visibly grounded at the worksite.

29 CFR 1926.1408(a)(2)(ii)

(ii) Option (2)—20 foot clearance. Ensure that no part of the equipment, load line, or load (including rigging and lifting accessories), gets closer than 20 feet to the power line by implementing the measures specified in paragraph (b) of this section.

29 CFR 1926.1428 · Signal person qualifications

29 CFR 1926.1430 · Training

Other structural steel and precast concrete contractors employers in Florida

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.