OSHA SearchOSHA records by employer

Cisneros Plastering LLC: OSHA inspections and violations

Vero Beach, Florida · Masonry Contractors · NAICS 238140

1inspections
7citation items
$6,518current penalties
Apr 4, 2017last inspection

Cisneros Plastering LLC has one OSHA inspection on record in Florida.

OSHA opened it on Apr 4, 2017 as a planned inspection, in Vero Beach.

From that inspection OSHA issued 7 citation items: 6 serious and 1 other-than-serious.

OSHA proposed $10,864 in penalties. After settlements and reviews the total is $6,518, down 40%.

Most often, OSHA cited 1926.451, scaffolds, general requirements (5 items).

For context, across all construction employers the median penalty per cited inspection since 2015 is $3,080. Cisneros Plastering LLC averages $6,518 over 1 cited inspection in that time.

Cisneros Plastering LLC: OSHA citation items per year, 2017 to 2017
Citation items per year, by inspection date.

Want to know if OSHA cites Cisneros Plastering LLC again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 342223906 OPENED APR 4, 2017Closed

Planned · Partial · Safety · 9 employees at the site · Closed Sep 5, 2018

979 Flamevine Lane, Vero Beach, FL 32963 · Masonry Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1926.451(b)(1) · Scaffolds, general requirements
Serious$2,716$1,630Apr 27, 2017Final
Citation 1, item 1b
29 CFR 1926.454(a) · Scaffold training
Serious$0$0Apr 27, 2017Final
Citation 1, item 2
29 CFR 1926.451(c)(2) · Scaffolds, general requirements
Serious$2,716$1,630Apr 27, 2017Final
Citation 1, item 3
29 CFR 1926.451(e)(1) · Scaffolds, general requirements
Serious$2,716$1,630Apr 27, 2017Final
Citation 1, item 4a
29 CFR 1926.451(g)(1) · Scaffolds, general requirements
Serious$2,716$1,630Apr 27, 2017Final
Citation 1, item 4b
29 CFR 1926.451(f)(7) · Scaffolds, general requirements
Serious$0$0Apr 27, 2017Final
Citation 2, item 1
29 CFR 1910.1200(e)(1) · Hazard communication
Other-than-serious$0$0Apr 27, 2017Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1910.1200 · Hazard communication

29 CFR 1910.1200(e)(1)

(e) Written hazard communication program. (1) Employers shall develop, implement, and maintain at each workplace, a written hazard communication program which at least describes how the criteria specified in paragraphs (f), (g), and (h) of this section for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes the following:

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.451(b)(1)

(b) Scaffold platform construction. (1) Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows:

29 CFR 1926.451(c)(2)

(2) Supported scaffold poles, legs, posts, frames, and uprights shall bear on base plates and mud sills or other adequate firm foundation.

29 CFR 1926.454 · Scaffold training