Since 2009, OSHA inspectors have visited Cityscape LLC in Virginia 4 times.
The most recent inspection opened on May 6, 2015, in Lynchburg.
In all, OSHA issued 6 citation items: 5 serious and 1 other-than-serious.
The proposed penalties came to $1,575; today they stand at $1,102, 30% less.
The rule cited most here is 1926.62 (lead in construction), 3 times.
Among construction employers, the typical cited inspection since 2015 ends with a $3,079 penalty. Cityscape LLC averages $551 across 2 cited inspections.
Inspection 314154055 OPENED MAR 2, 2010Closed
Planned · Partial · Safety · 4 employees at the site · Closed Mar 2, 2010
204 Jefferson Street, Roanoke, VA 24012 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
No citations from this inspection.
Inspection 314017393 OPENED DEC 1, 2009Closed
Unprogrammed related · Partial · Health · 3 employees at the site · Closed Dec 1, 2009
617 South Jefferson Street, Roanoke, VA 24011 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
No citations from this inspection.
Current text from the Code of Federal Regulations. Some citations were issued under older wording.
29 CFR 1926.1101(g)(1)(iii)
(iii) Prompt clean-up and disposal of wastes and debris contaminated with asbestos in leak-tight containers except in roofing operations, where the procedures specified in paragraph (g)(8)(ii) of this section apply.
29 CFR 1926.1101(k)(3)(i)
(i) Before work in areas containing ACM and PACM is begun; employers shall identify the presence, location, and quantity of ACM, and/or PACM therein pursuant to paragraph (k)(1)(i) of this section.
29 CFR 1926.1101(k)(9)(vi)
(vi) Training for employees performing Class IV operations shall be consistent with EPA requirements for training of local education agency maintenance and custodial staff as set forth at 40 CFR 763.92(a)(1). Such a course shall include available information concerning the locations of thermal system insulation and surfacing ACM/PACM, and asbestos-containing flooring material, or flooring material where the absence of asbestos has not yet been certified; and instruction in recognition of damage, deterioration, and delamination of asbestos containing building materials. Such course shall take at least 2 hours.
Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.