OSHA SearchOSHA records by employer

Daniel Gonsales: OSHA inspections and violations

Greenville, South Carolina · Masonry Contractors · NAICS 238140

1inspections
5citation items
$3,100current penalties
Jan 7, 2020last inspection

Daniel Gonsales has one OSHA inspection on record in South Carolina.

OSHA opened it on Jan 7, 2020 as a planned inspection, in Greenville.

From that inspection OSHA issued 5 citation items: 5 serious.

OSHA proposed $3,100 in penalties and the amount has not been reduced.

Most often, OSHA cited 1926.451, scaffolds, general requirements (4 items).

For context, across all construction employers the median penalty per cited inspection since 2015 is $3,079. Daniel Gonsales averages $3,100 over 1 cited inspection in that time.

Daniel Gonsales: OSHA citation items per year, 2020 to 2020
Citation items per year, by inspection date.

Want to know if OSHA cites Daniel Gonsales again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 344548037 OPENED JAN 7, 2020Closed

Planned · Partial · Safety · 4 employees at the site · Closed Oct 23, 2020

Rocky Slope Rd, Greenville, SC 29605 · Masonry Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.451(b)(1) · Scaffolds, general requirements
Serious$750$750Mar 19, 2020Final
Citation 1, item 2
29 CFR 1926.451(c)(1)(ii) · Scaffolds, general requirements
Serious$750$750Mar 19, 2020Final
Citation 1, item 3
29 CFR 1926.451(e)(1) · Scaffolds, general requirements
Serious$750$750Mar 19, 2020Final
Citation 1, item 4
29 CFR 1926.451(g)(1) · Scaffolds, general requirements
Serious$750$750Mar 19, 2020Final
Citation 1, item 5
29 CFR 1926.602(c)(1)(vi) · Earthmovers and forklifts in construction
Serious$100$100Mar 19, 2020Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.451(b)(1)

(b) Scaffold platform construction. (1) Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows:

29 CFR 1926.451(c)(1)(ii)

(ii) Guys, ties, and braces shall be installed according to the scaffold manufacturer's recommendations or at the closest horizontal member to the 4:1 height and be repeated vertically at locations of horizontal members every 20 feet (6.1 m) or less thereafter for scaffolds 3 feet (0.91 m) wide or less, and every 26 feet (7.9 m) or less thereafter for scaffolds greater than 3 feet (0.91 m) wide. The top guy, tie or brace of completed scaffolds shall be placed no further than the 4:1 height from the top. Such guys, ties and braces shall be installed at each end of the scaffold and at horizontal intervals not to exceed 30 feet (9.1 m) (measured from one end [not both] towards the other).

29 CFR 1926.451(e)(1)

(1) When scaffold platforms are more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access.

29 CFR 1926.602 · Earthmovers and forklifts in construction