OSHA SearchOSHA records by employer

E.L.S. Construction, Inc.: OSHA inspections and violations

Brighton, Michigan · Poured Concrete Foundation and Structure Contractors · NAICS 238110

3inspections
5citation items
$600current penalties
Oct 28, 2025last inspection

E.L.S. Construction, Inc. has 3 OSHA inspections on record in Michigan, the first in 2018.

OSHA's last visit started on Oct 28, 2025 as a planned inspection, in Detroit.

Across those inspections OSHA issued 5 citation items: 1 serious and 4 other-than-serious.

OSHA proposed $1,200 in penalties. After settlements and reviews the total is $600, down 50%.

For context, across all construction employers the median penalty per cited inspection since 2015 is $3,080. E.L.S. Construction, Inc. averages $300 over 2 cited inspections in that time.

E.L.S. Construction, Inc.: OSHA citation items per year, 2018 to 2025
Citation items per year, by inspection date.

Michigan · latest 90 days of OSHA records

647employers cited

17 of them in the same industry

Get notified the morning OSHA posts each new citation in Michigan: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Michigan

Checking a subcontractor, a client or your own company? Watch E.L.S. Construction, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 348577016 OPENED OCT 28, 2025Closed

Planned · Complete · Safety · 3 employees at the site · Closed Jan 21, 2026

4001 West Mcnichols Street, Detroit, MI 48221 · All Other Specialty Trade Contractors · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

Inspection 346215072 OPENED SEP 13, 2022Closed

Planned · Complete · Safety · 2 employees at the site · Closed Oct 12, 2022

10561 Grand River Avenue, Brighton, MI 48116 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 408.40114(1)
Other-than-serious$0$0Sep 28, 2022Final
Citation 1, item 2
29 CFR 408.41523(1)
Other-than-serious$0$0Sep 28, 2022Final
Citation 1, item 3
29 CFR 408.41524
Other-than-serious$0$0Sep 28, 2022Final

Inspection 342961950 OPENED FEB 21, 2018Closed

Planned · Complete · Safety · 5 employees at the site · Closed Apr 11, 2018

9968 E. Grand River, Brighton, MI 48116 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 408.40622(1)
Serious$1,200$600Mar 22, 2018Final
Citation 2, item 1
29 CFR 408.41523(1)
Other-than-serious$0$0Mar 22, 2018Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

Other poured concrete foundation and structure contractors employers in Michigan

Alert subscribers get notified of each newly cited employer in Michigan the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.