Detroit, Michigan · Electrical Contractors and Other Wiring Installation Contractors · NAICS 238210
4inspections
3citation items
$1,680current penalties
Mar 20, 2019last inspection
Since 2010, OSHA inspectors have visited Energy Group Inc in Michigan 4 times.
The most recent inspection opened on Mar 20, 2019 as a planned inspection, in Detroit.
In all, OSHA issued 3 citation items: 2 serious and 1 other-than-serious.
The proposed penalties came to $4,200; today they stand at $1,680, 60% less.
The rule cited most here is 1910.269 (electric power generation, transmission, and distribution), 2 times.
Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Energy Group Inc averages $0 across 1 cited inspection.
1 inspection on this page followed a fatal incident.
Energy Group Inc also files yearly injury logs with OSHA, summarized below.
Citation items per year, by inspection date.
Michigan · latest 90 days of OSHA records
647employers cited
24 of them in the same industry
Get notified the morning OSHA posts each new citation in Michigan: the employer, the site address, the rules broken and the penalty.
Incident on Aug 24, 2010 (fatal): Employee is electrocuted by electrical conductor
On August 24, 2010, Employee #1, an electrical lineman, was assigned the job tas k of connecting conductors, insulators, and cross arms, as well installing equip ment on electrical poles. While performing this job task, Employee #1 contacted a 4,800-volt electrical conductor that did not have insulating or shielding mate rial. Employee #1 was electrocuted and killed.
From the Form 300A summaries employers file with OSHA each year. Rate = recordable cases per 100 full-time workers.
In 2025, the Detroit site logged 4 recordable injuries or illnesses among about 203 workers: 1.6 per 100 full-time workers, against a median of 2.8 for its industry. Those cases cost 183 days away from work.
Site and year
Workers
Cases
Days-away cases
Rate
Industry median
Energy Group Inc.
Detroit · 2025
203
4
2
1.6
2.8
Energy Group, Inc
Detroit · 2023
166
2
0
0.9
2.8
The Energy Group, Inc.
Detroit · 2017
224
1
0
0.4
2.8
Included with any plan: 2 more yearly logs from these sites, back to 2017, with each site's average rate over its latest three years. Already a subscriber? Sign in.
Current text from the Code of Federal Regulations. Some citations were issued under older wording.
29 CFR 1910.269 · Electric power generation, transmission, and distribution
29 CFR 1910.269(a)(2)(iid)
(D) The proper use of the special precautionary techniques, personal protective equipment, insulating and shielding materials, and insulated tools for working on or near exposed energized parts of electric equipment, and
29 CFR 1910.269(a)(2)(iii)
(iii) Each line-clearance tree trimmer who is not a qualified employee shall also be trained and competent in:
(1) Each authorized entrant must use a chest or full body harness, with a retrieval line attached at the center of the entrant's back near shoulder level, above the entrant's head, or at another point which the employer can establish presents a profile small enough for the successful removal of the entrant. Wristlets or anklets may be used in lieu of the chest or full body harness if the employer can demonstrate that the use of a chest or full body harness is infeasible or creates a greater hazard and that the use of wristlets or anklets is the safest and most effective alternative.
Other electrical contractors and other wiring installation contractors employers in Michigan
Alert subscribers get notified of each newly cited employer in Michigan the morning it is posted. See the alert plans.
Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.