Inspection 341522548 OPENED JUN 1, 2016Closed
5565 Bright Cross Way Lot 5, Suwanee, GA 30024 · Masonry Contractors · OSHA's record · Phone and website on Google Maps
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|---|---|---|---|---|
| Citation 1, item 1a 29 CFR 1910.1200(e)(1) · Hazard communication |
Serious | $3,207 | $3,207 | Aug 25, 2016 | Final |
| Citation 1, item 1b 29 CFR 1910.1200(g)(8) · Hazard communication |
Serious | $0 | $0 | Aug 25, 2016 | Final |
| Citation 1, item 1c 29 CFR 1910.1200(h)(1) · Hazard communication |
Serious | $0 | $0 | Aug 25, 2016 | Final |
| Citation 1, item 3 29 CFR 1926.102(a)(1) · Eye and face protection in construction |
Serious | $3,207 | $3,207 | Aug 25, 2016 | Final |
| Citation 1, item 4 29 CFR 1926.300(b)(1) · Tools—Hand and Power: general requirements |
Serious | $2,673 | $2,673 | Aug 25, 2016 | Final |
| Citation 1, item 5 29 CFR 1926.451(b)(1) · Scaffolds, general requirements |
Serious | $3,742 | $3,742 | Aug 25, 2016 | Final |
| Citation 1, item 6 29 CFR 1926.451(e)(1) · Scaffolds, general requirements |
Serious | $3,742 | $3,742 | Aug 25, 2016 | Final |
| Citation 1, item 7 29 CFR 1926.451(g)(4)(i) · Scaffolds, general requirements |
Serious | $2,673 | $2,673 | Aug 25, 2016 | Final |
| Citation 1, item 8 29 CFR 1926.451(h)(1) · Scaffolds, general requirements |
Serious | $2,138 | $2,138 | Aug 25, 2016 | Final |
| Citation 1, item 9 29 CFR 1926.501(b)(13) · Fall protection in construction |
Serious | $3,742 | $3,742 | Aug 25, 2016 | Final |
| Citation 2, item 1 29 CFR 1903.19(c)(1) · Proving cited hazards were fixed |
Other-than-serious | $300 | $300 | Dec 13, 2016 | Final |
| Citation 2, item 2 29 CFR 1903.19(d)(1) · Proving cited hazards were fixed |
Other-than-serious | $300 | $300 | Dec 13, 2016 | Final |