OSHA SearchOSHA records by employer

Gary F. Gardner, Inc.: OSHA inspections and violations

Cherry Hill, New Jersey · Framing Contractors · NAICS 238130

4inspections
9citation items
$15,183current penalties
Feb 21, 2020last inspection

Gary F. Gardner, Inc. has 4 OSHA inspections on record in New Jersey, the first in 1984.

OSHA's last visit started on Feb 21, 2020 as a planned inspection, in Mount Laurel.

Across those inspections OSHA issued 9 citation items: 6 serious and 3 other-than-serious.

OSHA proposed $27,508 in penalties. After settlements and reviews the total is $15,183, down 45%.

Most often, OSHA cited 1926.500, scope, application, and definitions applicable to this subpart (3 items).

For context, across all construction employers the median penalty per cited inspection since 2015 is $3,080. Gary F. Gardner, Inc. averages $14,843 over 1 cited inspection in that time.

Gary F. Gardner, Inc.: OSHA citation items per year, 1984 to 2020
Citation items per year, by inspection date.

New Jersey · latest 90 days of OSHA records

276employers cited

20 of them in the same industry

Get notified the morning OSHA posts each new citation in New Jersey: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in New Jersey

Checking a subcontractor, a client or your own company? Watch Gary F. Gardner, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 344676671 OPENED FEB 21, 2020Closed

Planned · Partial · Safety · 60 employees at the site · Closed Sep 13, 2023

101 Centerton Rd, Mount Laurel, NJ 08054 · Framing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.451(e)(1) · Scaffolds, general requirements
Serious$8,096$7,422Jun 17, 2020Final
Citation 1, item 2
29 CFR 1926.451(g)(1) · Scaffolds, general requirements
Serious$9,446$7,422Jun 17, 2020Final
Citation 1, item 3
29 CFR 1926.454(a) · Scaffold training
Serious$9,446$0Jun 17, 2020Final

Inspection 340180728 OPENED DEC 22, 2014Closed

Unprogrammed related · Complete · Safety · 15 employees at the site · Closed Feb 17, 2015

157 7th Ave, Long Branch, NJ 07740 · Framing Contractors · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

Inspection 100194976 OPENED FEB 26, 1986Closed

Referral · Partial · Safety · 4 employees at the site · Closed Apr 3, 1986

Cropwell & Lincoln Roads, Evesham Twp., NJ 08054 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.25(a) · Housekeeping
Serious$180$90Mar 4, 1986Closed
Citation 1, item 2
29 CFR 1926.451(a)(4) · Scaffolds, general requirements
Serious$180$90Mar 4, 1986Closed

Inspection 122499 OPENED MAR 1, 1984Closed

Planned · Complete · Safety · 8 employees at the site · Closed Dec 31, 1996

Grove & Park Blvd, Cherry Hill, NJ 08034 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.500(b)(1) · Scope, application, and definitions applicable to this subpart
Serious$160$160Mar 6, 1984Closed
Citation 2, item 1
29 CFR 1926.400(h)(1) · Introduction
Other-than-serious$0$0Mar 6, 1984Closed
Citation 2, item 2
29 CFR 1926.500(c)(1) · Scope, application, and definitions applicable to this subpart
Other-than-serious$0$0Mar 6, 1984Closed
Citation 2, item 3
29 CFR 1926.500(e)(1)(ii) · Scope, application, and definitions applicable to this subpart
Other-than-serious$0$0Mar 6, 1984Closed

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.25 · Housekeeping

29 CFR 1926.25(a)

(a) During the course of construction, alteration, or repairs, form and scrap lumber with protruding nails, and all other debris, shall be kept cleared from work areas, passageways, and stairs, in and around buildings or other structures.

29 CFR 1926.400 · Introduction

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.451(a)(4)

(4) Each suspension rope, including connecting hardware, used on adjustable suspension scaffolds shall be capable of supporting, without failure, at least 6 times the maximum intended load applied or transmitted to that rope with the scaffold operating at either the rated load of the hoist, or 2 (minimum) times the stall load of the hoist, whichever is greater.

29 CFR 1926.451(e)(1)

(1) When scaffold platforms are more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access.

29 CFR 1926.454 · Scaffold training

29 CFR 1926.500 · Scope, application, and definitions applicable to this subpart

Other framing contractors employers in New Jersey

Alert subscribers get notified of each newly cited employer in New Jersey the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.