OSHA SearchOSHA records by employer

H&H Total Renovations LLC: OSHA inspections and violations

Bend, Oregon · Residential Remodelers · NAICS 236118

1inspections
1citation items
$1,177current penalties
Mar 19, 2025last inspection

OSHA inspectors have visited H&H Total Renovations LLC in Oregon one time.

It opened on Mar 19, 2025 after a complaint, in Bend.

In all, OSHA issued 1 citation item: 1 serious.

The penalties, $1,177 in total, stand where OSHA first set them.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. H&H Total Renovations LLC averages $1,177 across 1 cited inspection.

H&H Total Renovations LLC: OSHA citation items per year, 2025 to 2025
Citation items per year, by inspection date.

Oregon · latest 90 days of OSHA records

385employers cited

8 of them in the same industry

Get notified the morning OSHA posts each new citation in Oregon: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Oregon

Checking a subcontractor, a client or your own company? Watch H&H Total Renovations LLC and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 348123472 OPENED MAR 19, 2025Closed

Complaint · Partial · Safety · 5 employees at the site · Closed Oct 29, 2025

1695 Ne Purcell Blvd, Bend, OR 97701 · Residential Remodelers · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.452(j)(2) · Rules for each type of scaffold
Serious$1,177$1,177Apr 18, 2025Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.452 · Rules for each type of scaffold

29 CFR 1926.452(j)(2)

(2) Poles shall be secured to the structure by rigid triangular bracing or equivalent at the bottom, top, and other points as necessary. When the pump jack has to pass bracing already installed, an additional brace shall be installed approximately 4 feet (1.2 m) above the brace to be passed, and shall be left in place until the pump jack has been moved and the original brace reinstalled.

Other residential remodelers employers in Oregon