Hunt Electric Corporation: OSHA inspections and violations
Rochester, Minnesota · Electrical Contractors and Other Wiring Installation Contractors · NAICS 238210
74inspections
55citation items
$21,538current penalties
Jul 18, 2019last inspection
OSHA has inspected Hunt Electric Corporation 74 times in Minnesota since 1974.
The latest one began on Jul 18, 2019 as a planned inspection, in Rochester.
Those inspections ended with 55 citation items: 7 serious, 3 repeat and 45 other-than-serious.
Penalties were first proposed at $22,848 and now stand at $21,538, 6% lower after settlements or reviews.
Job-site wiring comes up most often in these citations: 14 items under 1926.405.
How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,080, and Hunt Electric Corporation averages $7,000 (1 cited inspection).
Hunt Electric Corporation also files yearly injury logs with OSHA, summarized below.
The Wage and Hour Division has 1 case on it since 2015, with $4,967 in back wages owed to workers.
Citation items per year, by inspection date.
Minnesota · latest 90 days of OSHA records
375employers cited
Get notified the morning OSHA posts each new citation in Minnesota: the employer, the site address, the rules broken and the penalty.
Incident on Dec 2, 1998: Two employees killed when crushed by gang box
At approximately 9:20 a.m. on December 2, 1998, ironworkers were attempting a bl ind lift with a Morrow/Liebherr 290 HC Tower Crane in order to hoist, stand, and position a 27-ft-tall 10,865-pound column on the eighth floor of the building. The operator of the tower crane began to hoist the north end of the column off t he metal floor decking of the eighth floor. When the operator had the column app roximately 5 ft off the metal decking the bottom of the column (south end) slipp ed off the wood planking that they were using to distribute the weight of the co lumn. As the column slipped off the wood damage, it began to rip a hole through the metal floor decking and dropped into the hole. The column then started to sw ing back and forth between the two I-beam floor-support members, bending the met al floor decking back towards the south I-beam floor support member. Then the co lumn swung back and struck the I-beam floor support member (facing north) causin g the I-beam to bend and bow out towards the north. This caused approximately fi ve sheets of metal floor decking (south) to breakaway and separate from the I-be am floor support member. Sitting on top of the five sheets of metal floor deckin g between the two I-beam floor support members, was a bolt box storage box. The box was approximately 8-ft by 8-ft with two 14-ft I-beam outriggers. The box and contents weighed approximately 6,100 pounds. The weight being exerted by the bo lt box on the five sheets of metal floor decking with their welds broken and sep arated from the I-beam floor-support member caused the metal floor decking to be nd down and created a hole for the bolt storage box to fall through. The bolt bo x continued to fall through the seventh floor. The box struck two employees on t he sixth floor and carried them through the sixth, fifth, fourth, and third floo rs. From the third floor the victims and the bolt box fell the remaining way thr ough an open atrium area and finally landing on the concrete floor on the first floor. Both Employees were killed.(NOTE: The injured employees were not listed o n the Injury Lines on the original form.)
No citations from this inspection.
Inspection 302093240 OPENED AUG 13, 1998Closed
Complaint · Partial · Safety · 8 employees at the site · Closed Aug 13, 1998
From the Form 300A summaries employers file with OSHA each year. Rate = recordable cases per 100 full-time workers.
In 2025, the Eagan site logged 7 recordable injuries or illnesses among about 980 workers: 0.7 per 100 full-time workers, against a median of 1.8 for its industry. Those cases cost 2 days away from work.
Site and year
Workers
Cases
Days-away cases
Rate
Industry median
Hunt Electric Corporation
Eagan · 2025
980
7
1
0.7
1.8
Hunt Electric Corporation Rochester
Rochester · 2025
61
1
0
1.6
1.8
Hunt Electric Corporation Mankato
Mankato · 2025
10
0
0
0.0
1.8
Hunt Electric Corporation
Bloomington · 2024
617
3
0
0.5
1.8
Corporate Headquarters
Bloomington · 2019
756
6
1
0.9
1.8
North Office
Duluth · 2019
156
1
1
0.7
1.8
South Office
Rochester · 2019
81
4
2
5.7
1.8
Included with any plan: 10 more yearly logs from these sites, back to 2017, with each site's average rate over its latest three years. Already a subscriber? Sign in.
(2) The employer shall instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his work environment to control or eliminate any hazards or other exposure to illness or injury.
(a) During the course of construction, alteration, or repairs, form and scrap lumber with protruding nails, and all other debris, shall be kept cleared from work areas, passageways, and stairs, in and around buildings or other structures.
(a) Installation safety requirements. Installation safety requirements are contained in §§ 1926.402 through 1926.408. Included in this category are electric equipment and installations used to provide electric power and light on jobsites.
Alert subscribers get notified of each newly cited employer in Minnesota the morning it is posted. See the alert plans.
Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.