OSHA SearchOSHA records by employer

IC Group LLC: OSHA inspections and violations

Murray, Utah · Printing · NAICS 323110

1inspections
10citation items
$1,750current penalties
Nov 25, 2019last inspection

OSHA inspectors have visited IC Group LLC in Utah one time.

It opened on Nov 25, 2019 as a planned inspection, in Murray.

In all, OSHA issued 10 citation items: 2 serious and 8 other-than-serious.

The proposed penalties came to $3,500; today they stand at $1,750, 50% less.

The rule cited most here is 1910.303 (electrical equipment, general requirements), 2 times.

Among manufacturing employers, the typical cited inspection since 2015 ends with a $4,500 penalty. IC Group LLC averages $1,750 across 1 cited inspection.

IC Group LLC: OSHA citation items per year, 2019 to 2019
Citation items per year, by inspection date.

Want to know if OSHA cites IC Group LLC again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 344471891 OPENED NOV 25, 2019Closed

Planned · Partial · Safety · 120 employees at the site · Closed Jan 27, 2020

4080 South 500 West, Murray, UT 84123 · Printing · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR UAC R614-1-5.C.7
Serious$3,500$1,750Dec 18, 2019Final
Citation 1, item 1b
29 CFR 1910.219(e)(1)(i) · Belts, pulleys and power-transmission parts
Serious$0$0Dec 18, 2019Final
Citation 2, item 1a
29 CFR 1910.147(c)(6)(i) · Lockout/tagout
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 1b
29 CFR 1910.147(c)(7)(iv) · Lockout/tagout
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 2a
29 CFR 1910.212(a)(1) · Machine guarding
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 2b
29 CFR 1910.212(b) · Machine guarding
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 3a
29 CFR 1910.303(b)(2) · Electrical equipment, general requirements
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 3b
29 CFR 1910.303(g)(1) · Electrical equipment, general requirements
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 3c
29 CFR 1910.304(b)(5) · Grounding and circuit protection
Other-than-serious$0$0Dec 18, 2019Final
Citation 2, item 3d
29 CFR 1910.305(a)(2) · Electrical wiring methods
Other-than-serious$0$0Dec 18, 2019Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1910.147 · Lockout/tagout

29 CFR 1910.147(c)(6)(i)

(6) Periodic inspection. (i) The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed.

29 CFR 1910.147(c)(7)(iv)

(iv) The employer shall certify that employee training has been accomplished and is being kept up to date. The certification shall contain each employee's name and dates of training.

29 CFR 1910.212 · Machine guarding

29 CFR 1910.212(a)(1)

(a) Machine guarding—(1) Types of guarding. One or more methods of machine guarding shall be provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks. Examples of guarding methods are—barrier guards, two-hand tripping devices, electronic safety devices, etc.

29 CFR 1910.219 · Belts, pulleys and power-transmission parts

29 CFR 1910.303 · Electrical equipment, general requirements

29 CFR 1910.304 · Grounding and circuit protection

29 CFR 1910.305 · Electrical wiring methods