Marietta, Georgia · Masonry Contractors · NAICS 238140

2inspections
4citation items
$13,741current penalties
Feb 2, 2021last inspection

Since 2011, OSHA inspectors have visited Jose Torres in Georgia 2 times.

The most recent inspection opened on Feb 2, 2021 as a planned inspection, in Dacula.

In all, OSHA issued 4 citation items: 4 serious.

The penalties, $13,741 in total, stand where OSHA first set them.

The rule cited most here is 1926.451 (scaffolds, general requirements), 3 times.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Jose Torres averages $2,341 across 1 cited inspection.

Jose Torres: OSHA citation items per year, 2011 to 2021
Citation items per year, by inspection date.

Georgia · latest 90 days of OSHA records

136employers cited

6 of them in the same industry

Get notified the morning OSHA posts each new citation in Georgia: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Georgia

Checking a subcontractor, a client or your own company? Watch Jose Torres and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 345134894 OPENED FEB 2, 2021Closed

Planned · Complete · Safety · 3 employees at the site · Closed Apr 2, 2024

2212 Alcovy Rd Se, Dacula, GA 30019 · Drywall and Insulation Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.501(b)(1) · Fall protection in construction
Serious$2,341$2,341Jun 16, 2021Final

Inspection 314644485 OPENED AUG 24, 2011Closed

Planned · Partial · Safety · 4 employees at the site · Closed Sep 10, 2014

3935 Wieuca Court, Marietta, GA 30066 · Masonry Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.451(b)(1) · Scaffolds, general requirements
Serious$4,200$4,200Oct 3, 2011Closed
Citation 1, item 2
29 CFR 1926.451(c)(2) · Scaffolds, general requirements
Serious$3,000$3,000Oct 3, 2011Closed
Citation 1, item 3
29 CFR 1926.451(g)(4)(i) · Scaffolds, general requirements
Serious$4,200$4,200Oct 3, 2011Closed

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.451(b)(1)

(b) Scaffold platform construction. (1) Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows:

29 CFR 1926.451(c)(2)

(2) Supported scaffold poles, legs, posts, frames, and uprights shall bear on base plates and mud sills or other adequate firm foundation.

29 CFR 1926.451(g)(4)(i)

(i) Guardrail systems shall be installed along all open sides and ends of platforms. Guardrail systems shall be installed before the scaffold is released for use by employees other than erection/dismantling crews.

29 CFR 1926.501 · Fall protection in construction

Other masonry contractors employers in Georgia

Alert subscribers get notified of each newly cited employer in Georgia the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.