OSHA SearchOSHA records by employer

Jsherman Construction LLC: OSHA inspections and violations

Durango, Colorado · Framing Contractors · NAICS 238130

1inspections
15citation items
$12,484current penalties
Jan 22, 2024last inspection

OSHA inspectors have visited Jsherman Construction LLC in Colorado one time.

It opened on Jan 22, 2024 on a referral, in Durango and is still open.

In all, OSHA issued 15 citation items: 14 serious and 1 other-than-serious.

The proposed penalties came to $24,583; today they stand at $12,484, 49% less.

The rule cited most here is 1926.1431 (hoisting personnel), 7 times.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Jsherman Construction LLC averages $12,484 across 1 cited inspection.

Jsherman Construction LLC: OSHA citation items per year, 2024 to 2024
Citation items per year, by inspection date.

Colorado · latest 90 days of OSHA records

134employers cited

24 of them in the same industry

Get notified the morning OSHA posts each new citation in Colorado: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Colorado

Checking a subcontractor, a client or your own company? Watch Jsherman Construction LLC and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 347245110 OPENED JAN 22, 2024Open

Referral · Partial · Safety · 3 employees at the site · Open

161 Double Diamond Dr., Durango, CO 81301 · Framing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.1404(a)(1) · Assembly/Disassembly—general requirements (applies to all assembly and disassembly operations)
Serious$4,839$2,096May 17, 2024Final
Citation 1, item 2a
29 CFR 1926.1412(d)(1) · Inspections
Serious$4,839$3,000May 17, 2024Final
Citation 1, item 2b
29 CFR 1926.1412(e)(1) · Inspections
Serious$0$0May 17, 2024Final
Citation 1, item 3 Serious$4,839$2,000May 17, 2024Final
Citation 1, item 4a
29 CFR 1926.1427(a) · Operator training, certification, and evaluation
Serious$4,839$2,000May 17, 2024Final
Citation 1, item 4b
29 CFR 1926.1427(f)(1)(i) · Operator training, certification, and evaluation
Serious$0$0May 17, 2024Final
Citation 1, item 4c
29 CFR 1926.1427(f)(1)(ii) · Operator training, certification, and evaluation
Serious$0$0May 17, 2024Final
Citation 1, item 5a
29 CFR 1926.1431(a) · Hoisting personnel
Serious$4,839$3,000May 17, 2024Final
Citation 1, item 5b
29 CFR 1926.1431(b)(1) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 1, item 5c
29 CFR 1926.1431(e)(1) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 1, item 5d
29 CFR 1926.1431(g)(1) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 1, item 5e
29 CFR 1926.1431(h)(1) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 1, item 5f
29 CFR 1926.1431(j)(1) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 1, item 5g
29 CFR 1926.1431(k)(10)(i) · Hoisting personnel
Serious$0$0May 17, 2024Final
Citation 2, item 1
29 CFR 1903.19(c)(1) · Proving cited hazards were fixed
Other-than-serious$388$388Jul 16, 2024Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1903.19 · Proving cited hazards were fixed

29 CFR 1903.19(c)(1)

(c) Abatement certification. (1) Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section.

29 CFR 1926.1404 · Assembly/Disassembly—general requirements (applies to all assembly and disassembly operations)

29 CFR 1926.1404(a)(1)

(a) Supervision—competent-qualified person. (1) Assembly/disassembly must be directed by a person who meets the criteria for both a competent person and a qualified person, or by a competent person who is assisted by one or more qualified persons (“A/D director”).

29 CFR 1926.1412 · Inspections

29 CFR 1926.1412(d)(1)

(d) Each shift. (1) A competent person must begin a visual inspection prior to each shift the equipment will be used, which must be completed before or during that shift. The inspection must consist of observation for apparent deficiencies. Taking apart equipment components and booming down is not required as part of this inspection unless the results of the visual inspection or trial operation indicate that further investigation necessitating taking apart equipment components or booming down is needed. Determinations made in conducting the inspection must be reassessed in light of observations made during operation. At a minimum the inspection must include all of the following:

29 CFR 1926.1417 · Operation

29 CFR 1926.1427 · Operator training, certification, and evaluation

29 CFR 1926.1431 · Hoisting personnel

Other framing contractors employers in Colorado

Alert subscribers get notified of each newly cited employer in Colorado the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.