OSHA SearchOSHA records by employer

Maduro Masonry Contractor, Inc.: OSHA inspections and violations

Providence, Rhode Island · Commercial and Institutional Building Construction · NAICS 236220

1inspections
5citation items
$3,716current penalties
Feb 4, 2026last inspection

OSHA inspectors have visited Maduro Masonry Contractor, Inc. in Rhode Island one time.

It opened on Feb 4, 2026 after a complaint, in Providence and is still open.

In all, OSHA issued 5 citation items: 2 serious and 3 other-than-serious.

The proposed penalties came to $5,163; today they stand at $3,716, 28% less.

The rule cited most here is 1903.19 (proving cited hazards were fixed), 2 times.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Maduro Masonry Contractor, Inc. averages $3,716 across 1 cited inspection.

Maduro Masonry Contractor, Inc.: OSHA citation items per year, 2026 to 2026
Citation items per year, by inspection date.

Rhode Island · latest 90 days of OSHA records

76employers cited

3 of them in the same industry

Get notified the morning OSHA posts each new citation in Rhode Island: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Rhode Island

Checking a subcontractor, a client or your own company? Watch Maduro Masonry Contractor, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 348724584 OPENED FEB 4, 2026Open

Complaint · Partial · Safety · 4 employees at the site · Open

55 George M Cohan Boulevard, Providence, RI 02906 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.300(b)(1) · Tools—Hand and Power: general requirements
Serious$2,412$1,688Mar 27, 2026Final
Citation 1, item 2
29 CFR 1926.701(b) · Concrete and Masonry Construction: general requirements
Serious$2,412$1,688Mar 27, 2026Final
Citation 2, item 1
29 CFR 1926.403(b)(2) · Electrical equipment on job sites
Other-than-serious$0$0Mar 27, 2026Final
Citation 3, item 1a
29 CFR 1903.19(c)(1) · Proving cited hazards were fixed
Other-than-serious$339$339Jul 31, 2026Open
Citation 3, item 1b
29 CFR 1903.19(d)(1) · Proving cited hazards were fixed
Other-than-serious$0$0Jul 31, 2026Open

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1903.19 · Proving cited hazards were fixed

29 CFR 1903.19(c)(1)

(c) Abatement certification. (1) Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section.

29 CFR 1903.19(d)(1)

(d) Abatement documentation. (1) The employer must submit to the Agency, along with the information on abatement certification required by paragraph (c)(3) of this section, documents demonstrating that abatement is complete for each willful or repeat violation and for any serious violation for which the Agency indicates in the citation that such abatement documentation is required.

29 CFR 1926.300 · Tools—Hand and Power: general requirements

29 CFR 1926.300(b)(1)

(b) Guarding. (1) When power operated tools are designed to accommodate guards, they shall be equipped with such guards when in use.

29 CFR 1926.403 · Electrical equipment on job sites

29 CFR 1926.701 · Concrete and Masonry Construction: general requirements

Other commercial and institutional building construction employers in Rhode Island

Alert subscribers get notified of each newly cited employer in Rhode Island the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.