OSHA SearchOSHA records by employer

Pablo Hernandez: OSHA inspections and violations

Cumming, Georgia · Masonry Contractors · NAICS 238140

3inspections
9citation items
$14,347current penalties
May 19, 2026last inspection

OSHA has inspected Pablo Hernandez 3 times in Georgia since 2007.

The latest one began on May 19, 2026, in Cumming; the case is still open.

Those inspections ended with 9 citation items: 8 serious and 1 other-than-serious.

Penalties were first proposed at $14,347 and still stand at $14,347.

Scaffolds, general requirements comes up most often in these citations: 5 items under 1926.451.

How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,080, and Pablo Hernandez averages $4,924 (2 cited inspections).

Pablo Hernandez: OSHA citation items per year, 2007 to 2026
Citation items per year, by inspection date.

Georgia · latest 90 days of OSHA records

138employers cited

6 of them in the same industry

Get notified the morning OSHA posts each new citation in Georgia: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Georgia

Checking a subcontractor, a client or your own company? Watch Pablo Hernandez and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 348945858 OPENED MAY 19, 2026Open

Inspection · Partial · Safety · 3 employees at the site · Open

5210 Memento Trace, Cumming, GA 30028 · Masonry Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1926.451(g)(1)(vii) · Scaffolds, general requirements
Serious$2,270$2,270May 29, 2026Final
Citation 1, item 2b
29 CFR 1926.454(a)(1) · Scaffold training
Serious$0$0May 29, 2026Final
Citation 2, item 1
29 CFR 1926.403(b)(1) · Electrical equipment on job sites
Other-than-serious$0$0May 29, 2026Final

Inspection 344322011 OPENED SEP 19, 2019Closed

Planned · Complete · Safety · 5 employees at the site · Closed Nov 8, 2022

Settendown Reserve Subdivision 5125 Minnow Lane, Lot #86, Cumming, GA 30028 · Siding Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.102(a)(1) · Eye and face protection in construction
Serious$2,273$2,273Sep 26, 2019Final
Citation 1, item 2
29 CFR 1926.451(g)(1) · Scaffolds, general requirements
Serious$5,304$5,304Sep 26, 2019Final

Inspection 309261865 OPENED MAR 28, 2007Closed

Planned · Partial · Safety · 9 employees at the site · Closed Oct 29, 2012

1006 Manchester Way, Roswell, GA 30075 · Masonry Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.451(b)(1) · Scaffolds, general requirements
Serious$1,500$1,500Apr 17, 2007Closed
Citation 1, item 2
29 CFR 1926.451(e)(1) · Scaffolds, general requirements
Serious$750$750Apr 17, 2007Closed
Citation 1, item 3
29 CFR 1926.451(g)(1) · Scaffolds, general requirements
Serious$1,500$1,500Apr 17, 2007Closed
Citation 1, item 4
29 CFR 1926.452(c)(3) · Rules for each type of scaffold
Serious$750$750Apr 17, 2007Closed

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.102 · Eye and face protection in construction

29 CFR 1926.102(a)(1)

(a) General. (1) The employer shall ensure that each affected employee uses appropriate eye or face protection when exposed to eye or face hazards from flying particles, molten metal, liquid chemicals, acids or caustic liquids, chemical gases or vapors, or potentially injurious light radiation.

29 CFR 1926.403 · Electrical equipment on job sites

29 CFR 1926.403(b)(1)

(b) Examination, installation, and use of equipment—(1) Examination. The employer shall ensure that electrical equipment is free from recognized hazards that are likely to cause death or serious physical harm to employees. Safety of equipment shall be determined on the basis of the following considerations:

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.451(b)(1)

(b) Scaffold platform construction. (1) Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports as follows:

29 CFR 1926.452 · Rules for each type of scaffold

29 CFR 1926.454 · Scaffold training

Other masonry contractors employers in Georgia

Alert subscribers get notified of each newly cited employer in Georgia the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.