Inspection 348074907 OPENED FEB 28, 2025Closed
507 Academy Road, Catonsville, MD 21228 · All Other Specialty Trade Contractors · OSHA's record · Phone and website on Google Maps
Incident on Feb 28, 2025 (fatal): Two employees are fatally injured when struck by falling fie
At 11:30 a.m. on February 28, 2025, Employee #1 and Employee #2 and Coworker #1 and Coworker #2 , were applying CTS Cement Rapid Set Mortar Mix on an exposed fieldstone foundation wall to reinforce the deteriorating wall. The crew was working inside a trench that was approximately 34-foot-long by 3-foot-wide by 6-foot-deep in type C soil. Employees #1 and Employee #2 were working in the eastern side of the trench while Coworker #1 and Coworker #2 were working in the southern side of the trench. Coworker #3, was also working inside the the eastern side of the trench, but was tasked to dig below the base of the foundation wall. Coworker #3 exited the trench and either Employee #1 or Employee #2 took Coworker #3's place. The foundation wall excavated and dug underneath the wall using shovels and a rotary hammer to create a concrete foundation. No cave-in protection or shoring was used. The eastern side of the wall fell into the trench striking Employee #1 and Employee #2, fatally injuring both employees.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|---|---|---|---|---|
| Citation 1, item 1a 29 CFR 1910.1200(e)(1) · Hazard communication |
Serious | $2,100 | $1,009 | Aug 25, 2025 | Final |
| Citation 1, item 1b 29 CFR 1910.1200(g)(1) · Hazard communication |
Serious | $0 | $0 | Aug 25, 2025 | Final |
| Citation 1, item 1c 29 CFR 1910.1200(h)(1) · Hazard communication |
Serious | $0 | $0 | Aug 25, 2025 | Final |
| Citation 1, item 2 29 CFR 1926.50(g) · Medical services and first aid |
Serious | $2,100 | $1,071 | Aug 25, 2025 | Final |
| Citation 1, item 3a 29 CFR 1926.100(a) · Hard hats in construction |
Serious | $2,100 | $1,071 | Aug 25, 2025 | Final |
| Citation 1, item 3b 29 CFR 1926.102(a)(1) · Eye and face protection in construction |
Serious | $0 | $0 | Aug 25, 2025 | Final |
| Citation 1, item 4 29 CFR 1926.651(j)(2) · Excavations |
Serious | $2,100 | $1,071 | Aug 25, 2025 | Final |
| Citation 1, item 5 29 CFR 1926.651(k)(1) · Excavations |
Serious | $2,800 | $1,428 | Aug 25, 2025 | Final |
| Citation 2, item 1 29 CFR 1926.21(b)(2) · Construction safety training |
Willful | $28,000 | $49,500 | Aug 25, 2025 | Final |
| Citation 2, item 2 29 CFR 1926.651(i)(1) · Excavations |
Willful | $28,000 | $6,900 | Aug 25, 2025 | Final |
| Citation 2, item 3 29 CFR 1926.651(i)(2) · Excavations |
Willful | $30,000 | $7,750 | Aug 25, 2025 | Final |
| Citation 2, item 4 29 CFR 1926.652(a)(1) · Trench protection |
Willful | $28,000 | $49,500 | Aug 25, 2025 | Final |
| Citation 3, item 1 29 CFR 1910.1200(e)(1)(i) · Hazard communication |
Other-than-serious | $1,050 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 2 29 CFR 1926.651(b)(1) · Excavations |
Other-than-serious | $1,050 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 3 29 CFR 1926.1053(b)(1) · Ladders in construction |
Other-than-serious | $1,050 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 4 29 CFR 1926.1053(b)(4) · Ladders in construction |
Other-than-serious | $1,050 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 5 29 CFR 1926.1053(b)(13) · Ladders in construction |
Other-than-serious | $1,050 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 6 29 CFR 5-503(A) |
Other-than-serious | $700 | $100 | Aug 25, 2025 | Final |
| Citation 3, item 7 29 CFR 05-503(C)(1)(I) |
Other-than-serious | $700 | $100 | Aug 25, 2025 | Final |