Cockeysville, Maryland · Commercial and Institutional Building Construction · NAICS 236220

8inspections
9citation items
$5,500current penalties
Apr 30, 2026last inspection

OSHA has inspected Rycon Construction, Inc. 8 times in Maryland since 1984.

The latest one began on Apr 30, 2026 as a planned inspection, in Annapolis; the case is still open.

Those inspections ended with 9 citation items: 3 serious and 6 other-than-serious.

Penalties were first proposed at $5,500 and still stand at $5,500.

Fall protection in construction comes up most often in these citations: 2 items under 1926.501.

How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,079, and Rycon Construction, Inc. averages $2,250 (2 cited inspections).

Rycon Construction, Inc.: OSHA citation items per year, 1984 to 2026
Citation items per year, by inspection date.

Want to know if OSHA cites Rycon Construction, Inc. again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 348914508 OPENED APR 30, 2026Open

Planned · Complete · Safety · 3 employees at the site · Open

2002 Annapolis Mall Road, Annapolis, MD 21401 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.403(i)(2)(i) · Electrical equipment on job sites
Serious$1,875$1,875Jul 9, 2026Contested
Citation 1, item 2
29 CFR 1926.1052(c)(1)(i) · Stairways in construction
Serious$2,625$2,625Jul 9, 2026Contested

Inspection 343209722 OPENED JUN 6, 2018Closed

Unprogrammed other · Complete · Safety · 1 employee at the site · Closed Aug 9, 2018

126 Shawan Road, Cockeysville, MD 21030 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.150(c)(1)(viii) · Fire protection
Other-than-serious$0$0Jul 31, 2018Final
Citation 1, item 2
29 CFR 1926.405(a)(2)(ii)(e) · Job-site wiring
Other-than-serious$0$0Jul 31, 2018Final

Inspection 315911453 OPENED AUG 17, 2011Closed

Planned · Complete · Safety · 1 employee at the site · Closed Aug 30, 2011

687 Mosser Road, Mchenry, MD 21541 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

Inspection 310509070 OPENED OCT 12, 2006Closed

Accident · Partial · Health · 8 employees at the site · Closed Nov 28, 2006

1275 West Patrick Street, Frederick, MD 21701 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

Incident on Oct 11, 2006: Two employees overcome by carbon monoxide gas

At approximately 10:30 p.m. on October 11, 2006, Employee #1, a saw operator, an d Employee #2 were renovating the meat preparation area of a grocery store. Empl oyee #1 was using a gasoline-powered concrete saw to cut the floor of the work a rea. They had been cutting for less than an hour when Employee #2 left for a bri ef period. Upon his return, he found Employee #1 slumped over. Employee #1 was p ulled out of the room, and emergency medical personnel were summoned. Upon their arrival, the fire department determined that the level of carbon monoxide was 4 50 ppm in the work area and 300 ppm in the back of the store. They cleared the b uilding and began ventilating it. Employee #1 was taken to a medical center, whe re he was treated in the hyperbaric chamber and then hospitalized. He had a carb oxyhemoglobin level of 37, which dropped to 18 after he was on oxygen for two to three hours and spent one-and-a-half to two hours in the hyperbaric chamber. Em ployee #2 was taken to a different hospital, where his carboxyhemoglobin level w as measured at 16.9. He received oxygen for two hours and was released. Even tho ugh ventilators were available, Employees #1 and #2 did not use them. They thoug ht they had adequate ventilation for the short duration of the job.

No citations from this inspection.

Inspection 310302328 OPENED JUL 20, 2006Closed

Planned · Complete · Safety · 4 employees at the site · Closed Nov 14, 2006

8665 Pulaski Highway, Rosedale, MD 21237 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.501(b)(4)(ii) · Fall protection in construction
Other-than-serious$0$0Aug 4, 2006Closed
Citation 1, item 2 Other-than-serious$0$0Aug 4, 2006Closed

Inspection 119571743 OPENED AUG 17, 1995Closed

Unprogrammed related · Partial · Safety · 2 employees at the site · Closed Jan 11, 1996

118 Shawan Road, Cockeysville, MD 21030 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.501(a)(2) · Fall protection in construction
Serious$1,000$1,000Dec 4, 1995Closed

Inspection 119519106 OPENED JUN 25, 1995Closed

Planned · Partial · Safety · 1 employee at the site · Closed Jul 12, 1995

5220 Campbell Boulevard, White Marsh, MD 21162 · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

Inspection 14842769 OPENED JUL 23, 1984Closed

Planned · Complete · Safety · 30 employees at the site · Closed Aug 28, 1984

Laurel Valley Garth & Parallel Path, Abingdon, MD 21009 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.150(a)(1) · Fire protection
Other-than-serious$0$0Aug 3, 1984Closed
Citation 1, item 2
29 CFR 1926.152(a)(1) · Flammable liquids
Other-than-serious$0$0Aug 3, 1984Closed

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 0912.2303

29 CFR 1926.1052 · Stairways in construction

29 CFR 1926.1052(c)(1)(i)

(i) At least one handrail; and

29 CFR 1926.150 · Fire protection

29 CFR 1926.150(a)(1)

(a) General requirements. (1) The employer shall be responsible for the development of a fire protection program to be followed throughout all phases of the construction and demolition work, and he shall provide for the firefighting equipment as specified in this subpart. As fire hazards occur, there shall be no delay in providing the necessary equipment.

29 CFR 1926.150(c)(1)(viii)

(viii) Portable fire extinguishers shall be inspected periodically and maintained in accordance with Maintenance and Use of Portable Fire Extinguishers, NFPA No. 10A-1970.

29 CFR 1926.152 · Flammable liquids

29 CFR 1926.403 · Electrical equipment on job sites

29 CFR 1926.405 · Job-site wiring

29 CFR 1926.501 · Fall protection in construction

Other commercial and institutional building construction employers in Maryland