OSHA inspectors have visited Ssci LLC in South Carolina one time.

It opened on Sep 11, 2025 as a planned inspection, in Rock Hill and is still open.

In all, OSHA issued 2 citation items: 2 other-than-serious.

The penalties, $300 in total, stand where OSHA first set them.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Ssci LLC averages $300 across 1 cited inspection.

Ssci LLC: OSHA citation items per year, 2025 to 2025
Citation items per year, by inspection date.

Want to know if OSHA cites Ssci LLC again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 348518267 OPENED SEP 11, 2025Open

Planned · Complete · Safety · 9 employees at the site · Open

2871 Heckle Blvd, Rock Hill, SC 29732 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.1200(f)(6) · Hazard communication
Other-than-serious$150$150Nov 4, 2025Final
Citation 1, item 2
29 CFR 1926.150(c)(1)(vi) · Fire protection
Other-than-serious$150$150Nov 4, 2025Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1910.1200 · Hazard communication

29 CFR 1910.1200(f)(6)

(6) Workplace labeling. Except as provided in paragraphs (f)(7) and (f)(8) of this section, the employer shall ensure that each container of hazardous chemicals in the workplace is labeled, tagged or marked with either:

29 CFR 1926.150 · Fire protection

29 CFR 1926.150(c)(1)(vi)

(vi) A fire extinguisher, rated not less than 10B, shall be provided within 50 feet of wherever more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas are being used on the jobsite. This requirement does not apply to the integral fuel tanks of motor vehicles.