OSHA has inspected Troy Morse Concrete, Inc. once in Maine.

The inspection began on Jan 22, 2015 on a referral, in Saco.

That inspection ended with 5 citation items: 4 serious and 1 other-than-serious.

Penalties were first proposed at $7,600 and now stand at $6,080, 20% lower after settlements or reviews.

Inspections comes up most often in these citations: 2 items under 1926.1412.

How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,080, and Troy Morse Concrete, Inc. averages $6,080 (1 cited inspection).

Troy Morse Concrete, Inc.: OSHA citation items per year, 2015 to 2015
Citation items per year, by inspection date.

Maine · latest 90 days of OSHA records

34employers cited

Get notified the morning OSHA posts each new citation in Maine: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Maine

Checking a subcontractor, a client or your own company? Watch Troy Morse Concrete, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 340212042 OPENED JAN 22, 2015Closed

Referral · Partial · Safety · 5 employees at the site · Closed Jun 20, 2017

438 Main Street, Saco, ME 04072 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.251(a)(4) · Rigging equipment for material handling
Serious$2,000$1,600Feb 18, 2015Final
Citation 1, item 2a
29 CFR 1926.1412(f)(2) · Inspections
Serious$2,800$2,240Feb 18, 2015Final
Citation 1, item 2b Serious$0$0Feb 18, 2015Final
Citation 1, item 3
29 CFR 1926.1434(a) · Equipment modifications
Serious$2,800$2,240Feb 18, 2015Final
Citation 2, item 1 Other-than-serious$0$0Feb 18, 2015Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.1412 · Inspections

29 CFR 1926.1412(e)(3)(i)

(3) Documentation. (i) The following information must be documented and maintained by the employer that conducts the inspection:

29 CFR 1926.1412(f)(2)

(2) In addition, at least every 12 months, the equipment must be inspected by a qualified person. Disassembly is required, as necessary, to complete the inspection. The equipment must be inspected for all of the following:

29 CFR 1926.1417 · Operation

29 CFR 1926.1417(c)(1)

(c) Accessibility of procedures. (1) The procedures applicable to the operation of the equipment, including rated capacities (load charts), recommended operating speeds, special hazard warnings, instructions, and operator's manual, must be readily available in the cab at all times for use by the operator.

29 CFR 1926.1434 · Equipment modifications

29 CFR 1926.251 · Rigging equipment for material handling

Other poured concrete foundation and structure contractors employers in Maine

Alert subscribers get notified of each newly cited employer in Maine the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.