OSHA has inspected Westech Systems, LLC 15 times in California since 2006.
The latest one began on Oct 17, 2025 as a planned inspection, in Clovis.
Those inspections ended with 9 citation items: 3 serious and 6 other-than-serious.
Penalties were first proposed at $67,105 and now stand at $43,560, 35% lower after settlements or reviews.
How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,079, and Westech Systems, LLC averages $10,781 (4 cited inspections).
1 inspection on this page followed a fatal incident.
Westech Systems, LLC also files yearly injury logs with OSHA, summarized below.
Inspection 347602005 OPENED JUL 3, 2024Closed
Planned · Partial · Safety · 3 employees at the site · Closed Dec 26, 2024
1240 North Crystal Avenue, Fresno, CA 93728 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
No citations from this inspection.
Inspection 347217747 OPENED JAN 17, 2024Closed
Planned · Partial · Safety · 101 employees at the site · Closed Jul 11, 2024
1240 N Crystal Ave., Fresno, CA 93728 · Electrical Contractors and Other Wiring Installation Contractors · OSHA's record · Phone and website on Google Maps
No citations from this inspection.
Inspection 345910509 OPENED APR 20, 2022Closed
Fatality or catastrophe · Partial · Safety · 101 employees at the site · Closed Apr 7, 2025
467 W. Quincy Ave., Clovis, CA 93611 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
Incident on Apr 20, 2022 (fatal): Employee installing solar system is killed in fall from roof
On April 20, 2022, at 11:54 a.m. an employe was working as a Foreman for a company hired to install a solar energy system on the rooftop of a private residence. The employee was located on the roof while Coworker #1, a Solar Installer, was working on the ground level preparing solar panels for installation. Coworker #2, also a Solar Installer, was sitting on the peak of the roof taking a break. Coworker #3, another Solar Installer, was also sitting on the peak of the roof next to Coworker #2. The employee was measuring the solar panel installation rails near the edge of the roof when he fell 10 feet to the ground below. The employee incurred a serious head injury and was killed.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|
| Citation 1, item 1 29 CFR 1509(A) |
Other-than-serious | $11,250 | $4,000 | Oct 13, 2022 | Final |
| Citation 2, item 2 29 CFR 1670(A) |
Serious | $25,000 | $18,000 | Oct 13, 2022 | Final |
Inspection 344607775 OPENED FEB 5, 2020Closed
Accident · Partial · Safety · 150 employees at the site · Closed Mar 26, 2020
3247 W. Noble, Visalia, CA 93277 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
Incident on Jan 22, 2020: Employee is burned in electric arc flash
At 1:15 p.m. on January 22, 2020, Employee #1 was removing fuses from a commercial building's switchboard and panels in preparation for demolition. Employee #1 removed one fuse from the main switchboard's 480-volt fuse box. Upon removing the second fuse, an electric arc flash occurred. Employee #1 was transported to the hospital and admitted for treatment of burns to the face, neck, and both hands.
No citations from this inspection.
Inspection 344416227 OPENED OCT 23, 2019Closed
Accident · Partial · Safety · 150 employees at the site · Closed Jan 20, 2021
570 N Magnolia, Clovis, CA 93611 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
Incident on Sep 25, 2019: Employee fractures ankle when scaffold collapses
At 3:30 p.m. on September 25, 2019, an employee was laying out proposed electrical work on a construction project. The employee was working from an existing scaffold when it collapsed. The employee fell from the scaffold and fractured his left ankle which required hospitalization.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|
| Citation 1, item 1 29 CFR 3203(A)(7)(D) |
Other-than-serious | $1,200 | $900 | Mar 25, 2020 | Final |
Inspection 343400032 OPENED JUL 6, 2018Closed
Planned · Partial · Safety · 11 employees at the site · Closed Nov 15, 2018
Ne Corner Of Flagstaff & Demaree, Visalia, CA 93291 · Commercial and Institutional Building Construction · OSHA's record · Phone and website on Google Maps
No citations from this inspection.
From the Form 300A summaries employers file with OSHA each year. Rate = recordable cases per 100 full-time workers.
In 2025, the Clovis site logged 7 recordable injuries or illnesses among about 205 workers: 3.3 per 100 full-time workers, against a median of 1.8 for its industry. Those cases cost 2 days away from work.
Current text from the Code of Federal Regulations. Some citations were issued under older wording.
Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.