OSHA SearchOSHA records by employer

29 CFR 1926.1407: Power line safety (up to 350 kV)—assembly and disassembly

Subpart CC—Cranes and Derricks in Construction

10citations since 2015
9employers cited
50%serious, willful or repeat
$1,038median penalty per item

OSHA has cited 29 CFR 1926.1407 10 times since 2015, against 9 employers. Penalties on these items add up to $33,517 at their current amounts.

Citations per year

The parts of the rule cited most

1926.1407(g) · 4 citations

(g) Posting of electrocution warnings. There must be at least one electrocution hazard warning conspicuously posted in the cab so that it is in view of the operator and (except for overhead gantry and tower cranes) at least two on the outside of the equipment.

1926.1407(d) · 3 citations

(d) Assembly/disassembly inside Table A clearance prohibited. No part of a crane/derrick, load line, or load (including rigging and lifting accessories), whether partially or fully assembled, is allowed closer than the minimum approach distance under Table A (see § 1926.1408) to a power line unless the employer has confirmed that the utility owner/operator has deenergized and (at the worksite) visibly grounded the power line.

1926.1407(b)(3) · 2 citations

(3) At least one of the following additional measures must be in place. The measure selected from this list must be effective in preventing encroachment.

1926.1407(a) · 1 citations

(a) Before assembling or disassembling equipment, the employer must determine if any part of the equipment, load line, or load (including rigging and lifting accessories) could get, in the direction or area of assembly/disassembly, closer than 20 feet to a power line during the assembly/disassembly process. If so, the employer must meet the requirements in Option (1), Option (2), or Option (3) of this section, as follows:

Industries cited most

  • Construction 10

States cited most

Recently cited employers