OSHA has cited 29 CFR 1926.752 47 times since 2015, against 45 employers. Penalties on these items add up to $140,826 at their current amounts.
Citations per year
The parts of the rule cited most
1926.752(b) · 17 citations
(b) Commencement of steel erection. A steel erection contractor shall not erect steel unless it has received written notification that the concrete in the footings, piers and walls or the mortar in the masonry piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection.
1926.752(a)(1) · 9 citations
(1) The concrete in the footings, piers and walls and the mortar in the masonry piers and walls has attained, on the basis of an appropriate ASTM standard test method of field-cured samples, either 75 percent of the intended minimum compressive design strength or sufficient strength to support the loads imposed during steel erection.
1926.752(d) · 6 citations
(d) Pre-planning of overhead hoisting operations. All hoisting operations in steel erection shall be pre-planned to ensure that the requirements of § 1926.753(d) are met.
1926.752(c)(2) · 5 citations
(2) A firm, properly graded, drained area, readily accessible to the work with adequate space for the safe storage of materials and the safe operation of the erector's equipment.
1926.752(a) · 4 citations
(a) Approval to begin steel erection. Before authorizing the commencement of steel erection, the controlling contractor shall ensure that the steel erector is provided with the following written notifications:
1926.752(e) · 3 citations
(e) Site-specific erection plan. Where employers elect, due to conditions specific to the site, to develop alternate means and methods that provide employee protection in accordance with § 1926.753(c)(5), § 1926.757(a)(4) or § 1926.757(e)(4), a site-specific erection plan shall be developed by a qualified person and be available at the work site. Guidelines for establishing a site-specific erection plan are contained in appendix A to this subpart.
1926.752(c)(1) · 2 citations
(1) Adequate access roads into and through the site for the safe delivery and movement of derricks, cranes, trucks, other necessary equipment, and the material to be erected and means and methods for pedestrian and vehicular control. Exception: this requirement does not apply to roads outside of the construction site.
1926.752(a)(2) · 1 citations
(2) Any repairs, replacements and modifications to the anchor bolts were conducted in accordance with § 1926.755(b).
Industries cited most
- Construction 46
- Wholesale Trade 1
States cited most
Recently cited employers
- Henry Gurtzweiler, Inc. Dundee, MI · Sep 16, 2026
- Schafer Construction, Inc. Howell, MI · Sep 16, 2026
- Kevin K Jacobs General Contracting Inc Pembroke, NC · Aug 27, 2026
- Sanilac Steel, Inc. Marlette, MI · Mar 12, 2026
- George W. Auch Company Livonia, MI · Feb 10, 2026