Inspection 346435761 OPENED JAN 13, 2023Closed
749 E. Oakwood Blvd., Chicago, IL 60653 · Residential Remodelers · OSHA's record · Phone and website on Google Maps
Incident on Jan 12, 2023 (fatal): Employee is killed in partial structural collapse
At 11:14 a.m. on January 12, 2023, an employee, a laborer, was constructing a masonry wall around the eastside basement stairwell area when the east wall of the building collapsed, trapping him under the debris. The fire department arrived onsite to conduct rescue operations and transported the employee to the hospital, where he was pronounced dead due to blunt force trauma injuries to his whole body.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|---|---|---|---|---|
| Citation 1, item 1a 29 CFR 1910.134(c)(1) · Respiratory protection |
Serious | $2,679 | $1,500 | Jun 8, 2023 | Final |
| Citation 1, item 1b 29 CFR 1910.134(e)(1) · Respiratory protection |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 1c 29 CFR 1910.134(f)(2) · Respiratory protection |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 1d 29 CFR 1910.134(k)(1) · Respiratory protection |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 2a 29 CFR 1926.20(b)(1) · Construction safety programs |
Serious | $3,349 | $1,750 | Jun 8, 2023 | Final |
| Citation 1, item 2b 29 CFR 1926.21(b)(2) · Construction safety training |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 2c 29 CFR 1926.454(a) · Scaffold training |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 3 29 CFR 1926.100(a) · Hard hats in construction |
Serious | $2,679 | $1,500 | Jun 8, 2023 | Final |
| Citation 1, item 4 29 CFR 1926.102(a)(1) · Eye and face protection in construction |
Serious | $4,688 | $2,500 | Jun 8, 2023 | Final |
| Citation 1, item 5 29 CFR 1926.300(b)(1) · Tools—Hand and Power: general requirements |
Serious | $2,679 | $1,500 | Jun 8, 2023 | Final |
| Citation 1, item 6 29 CFR 1926.451(b)(1) · Scaffolds, general requirements |
Serious | $4,688 | $2,500 | Jun 8, 2023 | Final |
| Citation 1, item 7a 29 CFR 1926.451(c)(2) · Scaffolds, general requirements |
Serious | $4,688 | $2,500 | Jun 8, 2023 | Final |
| Citation 1, item 7b 29 CFR 1926.451(f)(3) · Scaffolds, general requirements |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 7c 29 CFR 1926.451(f)(7) · Scaffolds, general requirements |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 8 29 CFR 1926.451(e)(1) · Scaffolds, general requirements |
Serious | $2,009 | $1,000 | Jun 8, 2023 | Final |
| Citation 1, item 9 29 CFR 1926.451(g)(4)(i) · Scaffolds, general requirements |
Serious | $4,688 | $2,500 | Jun 8, 2023 | Final |
| Citation 1, item 10a 29 CFR 1926.651(i)(2) · Excavations |
Serious | $15,625 | $12,625 | Jun 8, 2023 | Final |
| Citation 1, item 10b 29 CFR 1926.651(k)(1) · Excavations |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 11 29 CFR 1926.850(a) · Preparatory operations |
Serious | $15,625 | $12,625 | Jun 8, 2023 | Final |
| Citation 1, item 12a 29 CFR 1926.1153(c)(1) · Silica dust in construction |
Serious | $4,688 | $2,500 | Jun 8, 2023 | Final |
| Citation 1, item 12b 29 CFR 1926.1153(d)(1) · Silica dust in construction |
Serious | $0 | $0 | Jun 8, 2023 | Final |
| Citation 1, item 12c 29 CFR 1926.1153(g)(1) · Silica dust in construction |
Serious | $0 | $0 | Jun 8, 2023 | Final |