OSHA SearchOSHA records by employer

Edd Services LLC: OSHA inspections and violations

Oak Creek, Wisconsin · Roofing Contractors · NAICS 238160

3inspections
16citation items
$176,140current penalties
May 26, 2026last inspection

OSHA has inspected Edd Services LLC 3 times in Wisconsin since 2025.

The latest one began on May 26, 2026, in Hartford; the case is still open.

Those inspections ended with 16 citation items: 7 serious, 6 repeat and 3 other-than-serious.

Penalties were first proposed at $176,140 and still stand at $176,140.

Fall protection in construction comes up most often in these citations: 4 items under 1926.501.

How that compares: the median penalty per cited inspection for construction employers since 2015 is $3,079, and Edd Services LLC averages $58,713 (3 cited inspections).

Edd Services LLC: OSHA citation items per year, 2025 to 2026
Citation items per year, by inspection date.

Want to know if OSHA cites Edd Services LLC again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 348957796 OPENED MAY 26, 2026Open

Inspection · Partial · Safety · 13 employees at the site · Open

954-960 Autumn Ridge Lane, Hartford, WI 53027 · Roofing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.100(a) · Hard hats in construction
Serious$5,958$5,958Jun 1, 2026Final
Citation 2, item 1
29 CFR 1926.20(b)(2) · Construction safety programs
Repeat$11,916$11,916Jun 1, 2026Final
Citation 2, item 2
29 CFR 1926.501(b)(13) · Fall protection in construction
Repeat$29,790$29,790Jun 1, 2026Final
Citation 2, item 3
29 CFR 1926.502(d)(17) · Fall protection systems
Repeat$11,916$11,916Jun 1, 2026Final
Citation 2, item 4
29 CFR 1926.503(c)(3) · Fall protection training in construction
Repeat$29,790$29,790Jun 1, 2026Final
Citation 2, item 5
29 CFR 1926.1053(b)(1) · Ladders in construction
Repeat$21,281$21,281Jun 1, 2026Final

Inspection 348484239 OPENED SEP 4, 2025Open

Planned · Partial · Safety · 14 employees at the site · Open

3848 E. Hazelbranch Lane, Oak Creek, WI 53154 · Roofing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.1053(b)(1) · Ladders in construction
Serious$5,958$5,958Sep 25, 2025Final
Citation 2, item 1
29 CFR 1926.501(b)(13) · Fall protection in construction
Repeat$11,916$11,916Sep 25, 2025Final
Citation 3, item 1
29 CFR 1903.19(d)(1) · Proving cited hazards were fixed
Other-than-serious$478$478Feb 20, 2026Final

Inspection 348211913 OPENED APR 29, 2025Open

Planned · Partial · Safety · 13 employees at the site · Open

9691 S. Burrell St,, Oak Creek, WI 53154 · Roofing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.102(a)(1) · Eye and face protection in construction
Serious$6,620$6,620Sep 16, 2025Final
Citation 1, item 2
29 CFR 1926.501(b)(13) · Fall protection in construction
Serious$11,585$11,585Sep 16, 2025Final
Citation 1, item 3
29 CFR 1926.501(b)(15) · Fall protection in construction
Serious$9,931$9,931Sep 16, 2025Final
Citation 1, item 4
29 CFR 1926.502(d)(17) · Fall protection systems
Serious$6,620$6,620Sep 16, 2025Final
Citation 1, item 5
29 CFR 1926.1053(b)(1) · Ladders in construction
Serious$11,585$11,585Sep 16, 2025Final
Citation 2, item 1
29 CFR 1903.19(c)(1) · Proving cited hazards were fixed
Other-than-serious$398$398Dec 5, 2025Final
Citation 3, item 1
29 CFR 1903.19(d)(1) · Proving cited hazards were fixed
Other-than-serious$398$398Dec 5, 2025Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1903.19 · Proving cited hazards were fixed

29 CFR 1903.19(c)(1)

(c) Abatement certification. (1) Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section.

29 CFR 1903.19(d)(1)

(d) Abatement documentation. (1) The employer must submit to the Agency, along with the information on abatement certification required by paragraph (c)(3) of this section, documents demonstrating that abatement is complete for each willful or repeat violation and for any serious violation for which the Agency indicates in the citation that such abatement documentation is required.

29 CFR 1926.100 · Hard hats in construction

29 CFR 1926.100(a)

(a) Employees working in areas where there is a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns, shall be protected by protective helmets.

29 CFR 1926.102 · Eye and face protection in construction

29 CFR 1926.1053 · Ladders in construction

29 CFR 1926.20 · Construction safety programs

29 CFR 1926.501 · Fall protection in construction

29 CFR 1926.502 · Fall protection systems

29 CFR 1926.503 · Fall protection training in construction

Other roofing contractors employers in Wisconsin

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.