Edis Lagos: OSHA inspections and violations

Poolesville, Maryland · Siding Contractors · NAICS 238170

1inspections
8citation items
$2,025current penalties
Jan 16, 2015last inspection

OSHA inspectors have visited Edis Lagos in Maryland one time.

It opened on Jan 16, 2015 as a planned inspection, in Poolesville.

In all, OSHA issued 8 citation items: 7 serious and 1 other-than-serious.

The penalties, $2,025 in total, stand where OSHA first set them.

The rule cited most here is 1926.451 (scaffolds, general requirements), 3 times.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Edis Lagos averages $2,025 across 1 cited inspection.

Edis Lagos: OSHA citation items per year, 2015 to 2015
Citation items per year, by inspection date.

Want to know if OSHA cites Edis Lagos again? Add it to a watchlist and we will email you the morning the citation shows up.

Watch this company

Inspection history

Inspection 340188143 OPENED JAN 16, 2015Closed

Planned · Complete · Safety · 2 employees at the site · Closed Mar 23, 2016

18020 Bliss Dr., Poolesville, MD 20837 · Siding Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.20(b)(1) · Construction safety programs
Serious$750$750Feb 11, 2015Final
Citation 1, item 2
29 CFR 1926.300(a) · Tools—Hand and Power: general requirements
Serious$375$375Feb 11, 2015Final
Citation 1, item 3a
29 CFR 1926.451(c)(2) · Scaffolds, general requirements
Serious$900$900Feb 11, 2015Final
Citation 1, item 3b
29 CFR 1926.451(f)(3) · Scaffolds, general requirements
Serious$0$0Feb 11, 2015Final
Citation 1, item 3c
29 CFR 1926.451(g)(1)(vii) · Scaffolds, general requirements
Serious$0$0Feb 11, 2015Final
Citation 1, item 3d
29 CFR 1926.452(j)(2) · Rules for each type of scaffold
Serious$0$0Feb 11, 2015Final
Citation 1, item 3e
29 CFR 1926.454(a) · Scaffold training
Serious$0$0Feb 11, 2015Final
Citation 2, item 1
29 CFR 1926.405(g)(2)(iii) · Job-site wiring
Other-than-serious$0$0Feb 11, 2015Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1926.20 · Construction safety programs

29 CFR 1926.20(b)(1)

(b) Accident prevention responsibilities. (1) It shall be the responsibility of the employer to initiate and maintain such programs as may be necessary to comply with this part.

29 CFR 1926.300 · Tools—Hand and Power: general requirements

29 CFR 1926.300(a)

(a) Condition of tools. All hand and power tools and similar equipment, whether furnished by the employer or the employee, shall be maintained in a safe condition.

29 CFR 1926.405 · Job-site wiring

29 CFR 1926.405(g)(2)(iii)

(iii) Splices. Flexible cords shall be used only in continuous lengths without splice or tap. Hard service flexible cords No. 12 or larger may be repaired if spliced so that the splice retains the insulation, outer sheath properties, and usage characteristics of the cord being spliced.

29 CFR 1926.451 · Scaffolds, general requirements

29 CFR 1926.452 · Rules for each type of scaffold

29 CFR 1926.454 · Scaffold training

Other siding contractors employers in Maryland

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.