OSHA SearchOSHA records by employer

Ridgeline Exteriors, Inc.: OSHA inspections and violations

Rochester, New Hampshire · Roofing Contractors · NAICS 238160

1inspections
3citation items
$6,000current penalties
May 27, 2016last inspection

OSHA inspectors have visited Ridgeline Exteriors, Inc. in New Hampshire one time.

It opened on May 27, 2016 on a referral, in Rochester and is still open.

In all, OSHA issued 3 citation items: 2 serious and 1 other-than-serious.

The penalties, $6,000 in total, stand where OSHA first set them.

Among construction employers, the typical cited inspection since 2015 ends with a $3,080 penalty. Ridgeline Exteriors, Inc. averages $6,000 across 1 cited inspection.

Ridgeline Exteriors, Inc.: OSHA citation items per year, 2016 to 2016
Citation items per year, by inspection date.

New Hampshire · latest 90 days of OSHA records

55employers cited

24 of them in the same industry

Get notified the morning OSHA posts each new citation in New Hampshire: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in New Hampshire

Checking a subcontractor, a client or your own company? Watch Ridgeline Exteriors, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 341508125 OPENED MAY 27, 2016Open

Referral · Partial · Safety · 11 employees at the site · Open

511 Portland Street, Rochester, NH 03839 · Roofing Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.452(k)(2) · Rules for each type of scaffold
Serious$2,800$2,800Jul 14, 2016Final
Citation 1, item 2
29 CFR 1926.454(b)(3) · Scaffold training
Serious$2,800$2,800Jul 14, 2016Final
Citation 2, item 1
29 CFR 1903.19(c)(1) · Proving cited hazards were fixed
Other-than-serious$400$400Dec 6, 2016Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1903.19 · Proving cited hazards were fixed

29 CFR 1903.19(c)(1)

(c) Abatement certification. (1) Within 10 calendar days after the abatement date, the employer must certify to OSHA (the Agency) that each cited violation has been abated, except as provided in paragraph (c)(2) of this section.

29 CFR 1926.452 · Rules for each type of scaffold

29 CFR 1926.452(k)(2)

(2) All ladders used to support ladder jack scaffolds shall meet the requirements of subpart X of this part—Stairways and Ladders, except that job-made ladders shall not be used to support ladder jack scaffolds.

29 CFR 1926.454 · Scaffold training

29 CFR 1926.454(b)(3)

(3) The design criteria, maximum intended load-carrying capacity and intended use of the scaffold;

Other roofing contractors employers in New Hampshire

Alert subscribers get notified of each newly cited employer in New Hampshire the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.