Inspection 346337348 OPENED NOV 10, 2022Closed
0.75 Miles Due West Of 3306 Walkers Corner Road, Scott, AR 72142 · Other Heavy and Civil Engineering Construction · OSHA's record · Phone and website on Google Maps
Incident on Nov 9, 2022 (fatal): Employee is killed by carbon monoxide asphyxiation from exha
At 7:54 p.m. on November 9, 2022, an employee and two coworkers were using gasoline powered two inch dewatering pump to remove standing water from a 54 inch culvert. When the employee did not come out of the culvert in the expected time frame, he was found unconscious and unresponsive inside the culvert. The employee was killed by asphyxiation due to high carbon monoxide concentrations inside the culvert due to the pump's exhaust fumes.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|---|---|---|---|---|
| Citation 1, item 3 29 CFR 1926.55(a)(2) · Gases, vapors, fumes, dusts, and mists |
Serious | $6,250 | $6,250 | May 3, 2023 | Final |
| Citation 1, item 7a 29 CFR 1926.1203(a) · Confined Spaces in Construction: general requirements |
Serious | $6,250 | $6,250 | May 3, 2023 | Final |
| Citation 1, item 7b 29 CFR 1926.1207(a) · Training |
Serious | $6,250 | $0 | May 3, 2023 | Final |
| Citation 2, item 1a 29 CFR 1910.1200(g)(8) · Hazard communication |
Other-than-serious | $6,250 | $4,375 | May 3, 2023 | Final |
| Citation 2, item 1b 29 CFR 1910.1200(h)(1) · Hazard communication |
Other-than-serious | $0 | $0 | May 3, 2023 | Final |
| Citation 2, item 1c 29 CFR 1910.1200(h)(3)(iii) · Hazard communication |
Other-than-serious | $0 | $0 | May 3, 2023 | Final |
| Citation 2, item 2a 29 CFR 1926.20(b)(1) · Construction safety programs |
Other-than-serious | $6,250 | $4,375 | May 3, 2023 | Final |
| Citation 2, item 2b 29 CFR 1926.20(b)(2) · Construction safety programs |
Other-than-serious | $0 | $0 | May 3, 2023 | Final |
| Citation 2, item 2c 29 CFR 1926.21(b)(2) · Construction safety training |
Other-than-serious | $0 | $0 | May 3, 2023 | Final |
| Citation 2, item 3 29 CFR 1926.1203(d) · Confined Spaces in Construction: general requirements |
Other-than-serious | $6,250 | $4,375 | May 3, 2023 | Final |
| Citation 3, item 1 29 CFR 1903.19(c)(1) · Proving cited hazards were fixed |
Other-than-serious | $501 | $501 | Oct 6, 2023 | Final |
| Citation 3, item 2 29 CFR 1903.19(d)(1) · Proving cited hazards were fixed |
Other-than-serious | $501 | $501 | Oct 6, 2023 | Final |