OSHA SearchOSHA records by employer

Elemental Arthouse, Inc.: OSHA inspections and violations

Nashville, Tennessee · Ornamental and Architectural Metal Work Manufacturing · NAICS 332323

1inspections
14citation items
$4,185current penalties
Apr 26, 2022last inspection

OSHA has inspected Elemental Arthouse, Inc. once in Tennessee.

The inspection began on Apr 26, 2022 after a complaint, in Nashville.

That inspection ended with 14 citation items: 11 serious and 3 other-than-serious.

Penalties were first proposed at $4,650 and now stand at $4,185, 10% lower after settlements or reviews.

Spray painting and finishing comes up most often in these citations: 4 items under 1910.107.

How that compares: the median penalty per cited inspection for manufacturing employers since 2015 is $3,600, and Elemental Arthouse, Inc. averages $4,185 (1 cited inspection).

Elemental Arthouse, Inc.: OSHA citation items per year, 2022 to 2022
Citation items per year, by inspection date.

Tennessee · latest 90 days of OSHA records

342employers cited

Get notified the morning OSHA posts each new citation in Tennessee: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Tennessee

Checking a subcontractor, a client or your own company? Watch Elemental Arthouse, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 345919807 OPENED APR 26, 2022Closed

Complaint · Partial · Safety · 5 employees at the site · Closed Oct 18, 2022

4206 Charlotte Avenue, Nashville, TN 37209 · Ornamental and Architectural Metal Work Manufacturing · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.107(b)(5)(iv) · Spray painting and finishing
Serious$600$534Jul 22, 2022Final
Citation 1, item 2a
29 CFR 1910.107(b)(9) · Spray painting and finishing
Serious$600$534Jul 22, 2022Final
Citation 1, item 2b
29 CFR 1910.107(g)(2) · Spray painting and finishing
Serious$0$0Jul 22, 2022Final
Citation 1, item 3a
29 CFR 1910.134(e)(1) · Respiratory protection
Serious$700$635Jul 22, 2022Final
Citation 1, item 3b
29 CFR 1910.134(f)(2) · Respiratory protection
Serious$0$0Jul 22, 2022Final
Citation 1, item 3c
29 CFR 1910.134(h)(2)(i) · Respiratory protection
Serious$0$0Jul 22, 2022Final
Citation 1, item 4
29 CFR 1910.243(c)(3) · Guarding of portable powered tools
Serious$500$434Jul 22, 2022Final
Citation 1, item 5a
29 CFR 1910.303(b)(7) · Electrical equipment, general requirements
Serious$800$730Jul 22, 2022Final
Citation 1, item 5b
29 CFR 1910.305(d)(2) · Electrical wiring methods
Serious$0$0Jul 22, 2022Final
Citation 1, item 6
29 CFR 1910.305(b)(1)(ii) · Electrical wiring methods
Serious$600$534Jul 22, 2022Final
Citation 1, item 7
29 CFR 1910.305(g)(2)(iii) · Electrical wiring methods
Serious$600$534Jul 22, 2022Final
Citation 2, item 1
29 CFR 1910.107(b)(5)(i) · Spray painting and finishing
Other-than-serious$100$100Jul 22, 2022Final
Citation 2, item 2a
29 CFR 1910.1200(h)(1) · Hazard communication
Other-than-serious$150$150Jul 22, 2022Final
Citation 2, item 2b
29 CFR TDLWD RULE 800-01-09-.06(2)
Other-than-serious$0$0Jul 22, 2022Final

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1910.107 · Spray painting and finishing

29 CFR 1910.107(b)(5)(i)

(i) The spraying operations except electrostatic spraying operations shall be so designed, installed and maintained that the average air velocity over the open face of the booth (or booth cross section during spraying operations) shall be not less than 100 linear feet per minute. Electrostatic spraying operations may be conducted with an air velocity over the open face of the booth of not less than 60 linear feet per minute, or more, depending on the volume of the finishing material being applied and its flammability and explosion characteristics. Visible gauges or audible alarm or pressure activated devices shall be installed to indicate or insure that the required air velocity is maintained. Filter rolls shall be inspected to insure proper replacement of filter media.

29 CFR 1910.107(b)(5)(iv)

(iv) Space within the spray booth on the downstream and upstream sides of filters shall be protected with approved automatic sprinklers.

29 CFR 1910.107(b)(9)

(9) Cleaning. Spray booths shall be so installed that all portions are readily accessible for cleaning. A clear space of not less than 3 feet on all sides shall be kept free from storage or combustible construction.

29 CFR 1910.1200 · Hazard communication

29 CFR 1910.134 · Respiratory protection

29 CFR 1910.243 · Guarding of portable powered tools

29 CFR 1910.303 · Electrical equipment, general requirements

29 CFR 1910.305 · Electrical wiring methods

Other ornamental and architectural metal work manufacturing employers in Tennessee

Alert subscribers get notified of each newly cited employer in Tennessee the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.