OSHA SearchOSHA records by employer

Rex Lumber Company, Inc.: OSHA inspections and violations

South Windsor, Connecticut · Lumber, Plywood, Millwork, and Wood Panel Merchant Wholesalers · NAICS 423310

6inspections
63citation items
$33,266current penalties
Sep 2, 2020last inspection

Rex Lumber Company, Inc. has 6 OSHA inspections on record in Connecticut, the first in 2000.

OSHA's last visit started on Sep 2, 2020 on a referral, in South Windsor.

Across those inspections OSHA issued 63 citation items: 37 serious, 2 repeat and 24 other-than-serious.

OSHA proposed $59,206 in penalties. After settlements and reviews the total is $33,266, down 44%.

Most often, OSHA cited 1910.146, permit-required confined spaces (9 items).

For context, across all wholesale employers the median penalty per cited inspection since 2015 is $3,424. Rex Lumber Company, Inc. averages $10,000 over 1 cited inspection in that time.

Rex Lumber Company, Inc. also files yearly injury logs with OSHA, summarized below.

It reported 1 severe injury to OSHA since 2015.

Rex Lumber Company, Inc.: OSHA citation items per year, 2000 to 2020
Citation items per year, by inspection date.

Connecticut · latest 90 days of OSHA records

89employers cited

Get notified the morning OSHA posts each new citation in Connecticut: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Connecticut

Checking a subcontractor, a client or your own company? Watch Rex Lumber Company, Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 344909908 OPENED SEP 2, 2020Closed

Referral · Partial · Safety · 80 employees at the site · Closed Jul 23, 2026

489 Sullivan Avenue, South Windsor, CT 06074 · Lumber, Plywood, Millwork, and Wood Panel Merchant Wholesalers · OSHA's record · Phone and website on Google Maps

Incident on Aug 31, 2020: Employee fractures pelvis when struck by falling stack of lu

At 8:30 a.m. on August 31, 2020, an employee was loading a large bundle of lumber with a forklift onto an infeed machine that was approximately 3 1/2 feet from the floor level. The employee dismounted the forklift and went over to the bundle of lumber to cut the metal retaining strap holding it together. Some of the lumber fell approximately 3 1/2 feet off the infeed machine and pinned the employee underneath it. The bundle that was being handled was poplar, weighing 2.4 pounds per board foot. The bundle dimensions were approximately 30 inches high by 38-40 inches wide. Witnesses stated that approximately 12 to 15 boards were found on top of the employee. Each board, according to the Mill Manager, measured approximately 14-16 feet long by 8-10 inches wide by 1 1/2 inches thick. According to the Mill Manager, each board weighed 40 to 50 pounds. The approximate amount of weight on top of the employee was estimated between 480 pounds and 750 pounds. The employee suffered a fractured pelvis and was hospitalized.

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
OSH Act Section 5(a)(1) · General Duty Clause
Serious$11,470$6,500Nov 20, 2020Final
Citation 1, item 2
OSH Act Section 5(a)(1) · General Duty Clause
Serious$6,554$3,500Nov 20, 2020Final

Inspection 311762215 OPENED APR 29, 2009Closed

Complaint · Complete · Health · 100 employees at the site · Closed Jun 11, 2015

489 Sullivan Avenue, South Windsor, CT 06074 · Lumber, Plywood, Millwork, and Wood Panel Merchant Wholesalers · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.23(c)(1) · Guarding floor and wall openings and holes
Serious$1,250$1,250Jun 8, 2009Closed
Citation 1, item 2a
29 CFR 1910.37(a)(3) · Exit routes
Other-than-serious$1,750$0Jun 8, 2009Closed
Citation 1, item 2b
29 CFR 1910.37(a)(4) · Exit routes
Other-than-serious$0$0Jun 8, 2009Closed
Citation 1, item 3
29 CFR 1910.37(b)(5) · Exit routes
Other-than-serious$1,750$0Jun 8, 2009Closed
Citation 1, item 4a
29 CFR 1910.133(a)(1) · Eye and face protection
Serious$1,250$1,250Jun 8, 2009Closed
Citation 1, item 4b
29 CFR 1910.138(a) · Gloves and hand protection
Other-than-serious$0$0Jun 8, 2009Closed
Citation 1, item 5
29 CFR 1910.147(c)(6)(i) · Lockout/tagout
Serious$1,000$1,000Jun 8, 2009Closed
Citation 1, item 6
29 CFR 1910.157(g)(2) · Portable fire extinguishers
Serious$1,750$750Jun 8, 2009Closed
Citation 1, item 8
29 CFR 1910.178(p)(1) · Forklifts and other powered industrial trucks
Other-than-serious$1,000$0Jun 8, 2009Closed
Citation 1, item 9
29 CFR 1910.212(a)(1) · Machine guarding
Serious$1,250$625Jun 8, 2009Closed
Citation 1, item 10
29 CFR 1910.212(a)(5) · Machine guarding
Other-than-serious$1,000$0Jun 8, 2009Closed
Citation 1, item 13
29 CFR 1910.215(b)(9) · Grinders and abrasive wheels
Serious$750$750Jun 8, 2009Closed
Citation 1, item 14
29 CFR 1910.219(d)(1) · Belts, pulleys and power-transmission parts
Serious$1,000$500Jun 8, 2009Closed
Citation 1, item 15
29 CFR 1910.219(f)(1) · Belts, pulleys and power-transmission parts
Serious$1,750$1,200Jun 8, 2009Closed
Citation 1, item 21
29 CFR 1910.1030(f)(1)(i) · Bloodborne pathogens
Serious$1,250$625Jun 8, 2009Closed
Citation 2, item 1
29 CFR 1910.132(d)(1) · Personal protective equipment, general requirements
Other-than-serious$0$0Jun 8, 2009Closed
Citation 2, item 2
29 CFR 1910.134(k)(6) · Respiratory protection
Other-than-serious$0$0Jun 8, 2009Closed
Citation 2, item 3
29 CFR 1910.146(c)(4) · Permit-required confined spaces
Other-than-serious$0$0Jun 8, 2009Closed
Citation 2, item 5
29 CFR 1910.1030(c)(1)(iv) · Bloodborne pathogens
Other-than-serious$0$0Jun 8, 2009Closed
Citation 2, item 6
29 CFR 1910.1030(g)(2)(iib) · Bloodborne pathogens
Other-than-serious$0$0Jun 8, 2009Closed
Citation 3, item 1a
29 CFR 1910.213(g)(1) · Woodworking machinery
Serious$0$1,250Jun 8, 2009Closed
Citation 3, item 1b
29 CFR 1910.213(i)(1) · Woodworking machinery
Serious$0$0Jun 8, 2009Closed
Citation 3, item 2a
29 CFR 1910.305(a)(1)(i) · Electrical wiring methods
Serious$0$750Jun 8, 2009Closed
Citation 3, item 2b
29 CFR 1910.305(g)(1)(iiib) · Electrical wiring methods
Serious$0$0Jun 8, 2009Closed
Citation 3, item 2c
29 CFR 1910.334(a)(2)(ii) · Using electrical equipment
Serious$0$0Jun 8, 2009Closed
Citation 3, item 3a
29 CFR 1910.305(e)(1) · Electrical wiring methods
Serious$0$1,000Jun 8, 2009Closed
Citation 3, item 3b
29 CFR 1910.305(g)(1)(iva) · Electrical wiring methods
Serious$0$0Jun 8, 2009Closed
Citation 3, item 3c
29 CFR 1910.305(g)(5) · Electrical wiring methods
Serious$0$0Jun 8, 2009Closed

Inspection 306413899 OPENED APR 20, 2004Closed

Planned · Complete · Safety · 130 employees at the site · Closed Aug 10, 2004

489 Sullivan Avenue, South Windsor, CT 06074 · Lumber, Plywood, Millwork, and Wood Panel Merchant Wholesalers · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.110(e)(4)(iii) · Storage and handling of liquefied petroleum gases
Serious$1,083$542Apr 23, 2004Closed
Citation 1, item 2
29 CFR 1910.157(g)(2) · Portable fire extinguishers
Serious$1,275$638Apr 23, 2004Closed
Citation 1, item 3
29 CFR 1910.178(p)(1) · Forklifts and other powered industrial trucks
Serious$1,275$638Apr 23, 2004Closed
Citation 1, item 4a
29 CFR 1910.213(b)(6) · Woodworking machinery
Serious$2,125$1,062Apr 23, 2004Closed
Citation 1, item 4b
29 CFR 1910.213(i)(1) · Woodworking machinery
Serious$0$0Apr 23, 2004Closed
Citation 1, item 5a
29 CFR 1910.219(d)(1) · Belts, pulleys and power-transmission parts
Serious$1,083$542Apr 23, 2004Closed
Citation 1, item 5b
29 CFR 1910.219(e)(3)(i) · Belts, pulleys and power-transmission parts
Serious$0$0Apr 23, 2004Closed
Citation 1, item 6
29 CFR 1910.253(b)(4)(iii) · Gas welding and cutting
Serious$1,083$542Apr 23, 2004Closed
Citation 1, item 7a
29 CFR 1910.303(g)(1)(ii) · Electrical equipment, general requirements
Serious$1,083$542Apr 23, 2004Closed
Citation 1, item 7b
29 CFR 1910.305(b)(2) · Electrical wiring methods
Serious$0$0Apr 23, 2004Closed
Citation 1, item 8a
29 CFR 1910.304(f)(4) · Grounding and circuit protection
Serious$1,700$850Apr 23, 2004Closed
Citation 1, item 8b
29 CFR 1910.304(f)(5)(v) · Grounding and circuit protection
Serious$0$0Apr 23, 2004Closed
Citation 2, item 1
29 CFR 1910.147(c)(4)(i) · Lockout/tagout
Other-than-serious$200$100Apr 23, 2004Closed
Citation 2, item 2
29 CFR 1910.147(c)(6)(i) · Lockout/tagout
Other-than-serious$200$100Apr 23, 2004Closed
Citation 3, item 1
29 CFR 1910.147(c)(6)(ia) · Lockout/tagout
Other-than-serious$0$0Apr 23, 2004Closed
Citation 3, item 2
29 CFR 1910.178(a)(6) · Forklifts and other powered industrial trucks
Other-than-serious$0$0Apr 23, 2004Closed
Citation 3, item 3
29 CFR 1910.212(b) · Machine guarding
Other-than-serious$0$0Apr 23, 2004Closed

Inspection 300083284 OPENED DEC 27, 2000Closed

Follow-up · Partial · Safety · 144 employees at the site · Closed Feb 20, 2001

489 Sullivan Avenue, South Windsor, CT 06074 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1910.146(d)(9) · Permit-required confined spaces
Repeat$200$200Dec 29, 2000Closed
Citation 1, item 1b
29 CFR 1910.146(g)(1) · Permit-required confined spaces
Repeat$0$0Dec 29, 2000Closed

Inspection 123203531 OPENED JUL 25, 2000Closed

Planned · Complete · Safety · 144 employees at the site · Closed Jan 2, 2001

489 Sullivan Avenue, South Windsor, CT 06074 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.213(n)(1) · Woodworking machinery
Serious$1,875$938Sep 11, 2000Closed
Citation 1, item 2
29 CFR 1910.213(r)(4) · Woodworking machinery
Serious$1,875$938Sep 11, 2000Closed
Citation 1, item 3
29 CFR 1910.219(e)(3)(i) · Belts, pulleys and power-transmission parts
Serious$1,875$938Sep 11, 2000Closed
Citation 1, item 4
29 CFR 1910.303(g)(2)(i) · Electrical equipment, general requirements
Serious$1,875$938Sep 11, 2000Closed
Citation 2, item 1
29 CFR 1910.37(q)(2) · Exit routes
Other-than-serious$0$0Sep 11, 2000Closed

Inspection 123203556 OPENED JUL 25, 2000Closed

Planned · Complete · Health · 144 employees at the site · Closed Jan 2, 2001

489 Sullivan Avenue, South Windsor, CT 06074 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1910.132(a) · Personal protective equipment, general requirements
Serious$1,125$562Sep 11, 2000Closed
Citation 1, item 1b
29 CFR 1910.132(d)(2) · Personal protective equipment, general requirements
Serious$0$0Sep 11, 2000Closed
Citation 1, item 2a
29 CFR 1910.146(c)(1) · Permit-required confined spaces
Other-than-serious$4,500$2,250Sep 11, 2000Closed
Citation 1, item 2b
29 CFR 1910.146(c)(2) · Permit-required confined spaces
Other-than-serious$0$0Sep 11, 2000Closed
Citation 1, item 2c
29 CFR 1910.146(c)(4) · Permit-required confined spaces
Other-than-serious$0$0Sep 11, 2000Closed
Citation 1, item 2d
29 CFR 1910.146(d)(4) · Permit-required confined spaces
Other-than-serious$0$0Sep 11, 2000Closed
Citation 1, item 2e
29 CFR 1910.146(d)(9) · Permit-required confined spaces
Other-than-serious$0$0Sep 11, 2000Closed
Citation 1, item 2f
29 CFR 1910.146(g)(1) · Permit-required confined spaces
Other-than-serious$0$0Sep 11, 2000Closed
Citation 2, item 1
29 CFR 1910.242(b) · Hand and power tools
Other-than-serious$0$0Sep 11, 2000Closed

Injury and illness logs

From the Form 300A summaries employers file with OSHA each year. Rate = recordable cases per 100 full-time workers.

In 2023, the South Windsor site logged 1 recordable injury or illness among about 89 workers: 1.3 per 100 full-time workers, against a median of 4.6 for its industry.

Site and yearWorkersCasesDays-away casesRateIndustry median
Rex Lumber Co CT yard
South Windsor · 2023
89 101.34.6
Rex Lumber Co
South Windsor · 2019
84 607.44.6

Included with any plan: 2 more yearly logs from these sites, back to 2016, with each site's average rate over its latest three years. Already a subscriber? Sign in.

See plans

Severe injury reports

Employers must report any work-related amputation, in-patient hospitalization or loss of an eye to OSHA within 24 hours. 1 report on file.

Aug 31, 2020, South Windsor: Hospitalization · fractures · hip(s)

An employee cut the strap on a bundle of lumber and it collapsed on him, breaking his hip. He was hospitalized.

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1910.1030 · Bloodborne pathogens

29 CFR 1910.1030(c)(1)(iv)

(iv) The Exposure Control Plan shall be reviewed and updated at least annually and whenever necessary to reflect new or modified tasks and procedures which affect occupational exposure and to reflect new or revised employee positions with occupational exposure. The review and update of such plans shall also:

29 CFR 1910.1030(f)(1)(i)

(f) Hepatitis B vaccination and post-exposure evaluation and follow-up—(1) General. (i) The employer shall make available the hepatitis B vaccine and vaccination series to all employees who have occupational exposure, and post-exposure evaluation and follow-up to all employees who have had an exposure incident.

29 CFR 1910.1030(g)(2)(iib)

(B) At least annually thereafter.

29 CFR 1910.110 · Storage and handling of liquefied petroleum gases

29 CFR 1910.132 · Personal protective equipment, general requirements

29 CFR 1910.133 · Eye and face protection

29 CFR 1910.134 · Respiratory protection

29 CFR 1910.138 · Gloves and hand protection

29 CFR 1910.146 · Permit-required confined spaces

29 CFR 1910.147 · Lockout/tagout

29 CFR 1910.157 · Portable fire extinguishers

29 CFR 1910.178 · Forklifts and other powered industrial trucks

29 CFR 1910.212 · Machine guarding

29 CFR 1910.213 · Woodworking machinery

29 CFR 1910.215 · Grinders and abrasive wheels

29 CFR 1910.219 · Belts, pulleys and power-transmission parts

29 CFR 1910.23 · Guarding floor and wall openings and holes

29 CFR 1910.242 · Hand and power tools

29 CFR 1910.253 · Gas welding and cutting

29 CFR 1910.303 · Electrical equipment, general requirements

29 CFR 1910.304 · Grounding and circuit protection

29 CFR 1910.305 · Electrical wiring methods

29 CFR 1910.334 · Using electrical equipment

29 CFR 1910.37 · Exit routes

OSH Act Section 5 · General Duty Clause

Other lumber, plywood, millwork, and wood panel merchant wholesalers employers in Connecticut

Alert subscribers get notified of each newly cited employer in Connecticut the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.