Swain Construction Inc. has 6 OSHA inspections on record in Nebraska, the first in 1995.

OSHA's last visit started on Aug 26, 2016 as a planned inspection, in Omaha.

Across those inspections OSHA issued 21 citation items: 10 serious, 1 repeat and 10 other-than-serious.

OSHA proposed $80,790 in penalties. After settlements and reviews the total is $72,480, down 10%.

Most often, OSHA cited 1910.147, lockout/tagout (4 items).

For context, across all construction employers the median penalty per cited inspection since 2015 is $3,080. Swain Construction Inc. averages $11,000 over 1 cited inspection in that time.

Swain Construction Inc.: OSHA citation items per year, 1995 to 2016
Citation items per year, by inspection date.

Nebraska · latest 90 days of OSHA records

31employers cited

Get notified the morning OSHA posts each new citation in Nebraska: the employer, the site address, the rules broken and the penalty.

See who gets cited next

Latest cited in Nebraska

Checking a subcontractor, a client or your own company? Watch Swain Construction Inc. and get notified the morning OSHA posts a new citation for it.

Watch this company

Inspection history

Inspection 341742542 OPENED AUG 26, 2016Closed

Planned · Partial · Safety · 60 employees at the site · Closed Mar 28, 2017

6002 N. 89th Circle, Omaha, NE 68134 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1a
29 CFR 1910.147(c)(4)(i) · Lockout/tagout
Other-than-serious$3,802$0Feb 13, 2017Final
Citation 1, item 2 Serious$6,338$4,000Feb 13, 2017Final
Citation 1, item 3
29 CFR 1910.1200(h)(1) · Hazard communication
Serious$3,802$3,000Feb 13, 2017Final
Citation 2, item 1
29 CFR 1904.39(a)(2) · Reporting deaths and severe injuries
Other-than-serious$6,338$4,000Feb 13, 2017Final

Inspection 316019157 OPENED JAN 13, 2012Closed

Follow-up · Partial · Safety · 65 employees at the site · Closed Dec 19, 2013

6002 N. 89th Circle, Omaha, NE 68134 · Poured Concrete Foundation and Structure Contractors · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1910.215(b)(9) · Grinders and abrasive wheels
Other-than-serious$6,160$1,000Feb 13, 2012Final

Inspection 314054602 OPENED APR 15, 2010Closed

Referral · Partial · Safety · 65 employees at the site · Closed Dec 19, 2013

88th And Maple Streets, Omaha, NE 68111 · All Other Specialty Trade Contractors · OSHA's record · Phone and website on Google Maps

Incident on Apr 14, 2010: Employee is injured by loader arm of skid steer

At approximately 8:10 p.m. on April 14, 2010, an employee was exiting a Case Ski d Steer, Model Number 450, and the raised loader arms lowered and trapped him ag ainst the machine and the ground. The employee sustained injuries including a fr actured orbital bone, multiple fractured ribs on the right side of the torso, a fractured pelvis, a fracture to the L4 vertebrae, and a contusion to the liver. He was transported to St. Josephs Medical Center in Omaha, NE, where he was hosp italized. This was a road construction site, and the employee was involved in th e installation of storm sewer inlets which run along the side of the road. These were precast units that included the inlet and vault area. The investigation re vealed that the lift arm bypass control lever used in the event that electrical power was lost while the loader lift arms were raised. It had been bolted into t he bypass position.

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.20(b)(2) · Construction safety programs
Repeat$6,300$31,500Sep 27, 2010Final
Citation 1, item 2
29 CFR 1910.22(a)(1) · General requirements
Other-than-serious$1,350$50Sep 27, 2010Final
Citation 1, item 3
29 CFR 1910.22(d)(1) · General requirements
Other-than-serious$1,800$50Sep 27, 2010Final
Citation 1, item 4
29 CFR 1910.23(d)(1) · Guarding floor and wall openings and holes
Serious$2,250$2,250Sep 27, 2010Final
Citation 1, item 5
29 CFR 1910.147(c)(1) · Lockout/tagout
Serious$6,300$6,300Sep 27, 2010Final
Citation 1, item 6
29 CFR 1910.147(c)(7)(i) · Lockout/tagout
Serious$6,300$0Sep 27, 2010Final
Citation 1, item 7
29 CFR 1910.212(a)(1) · Machine guarding
Serious$4,500$4,500Sep 27, 2010Final
Citation 1, item 8a
29 CFR 1910.215(a)(4) · Grinders and abrasive wheels
Other-than-serious$1,800$50Sep 27, 2010Final
Citation 1, item 8b
29 CFR 1910.215(b)(9) · Grinders and abrasive wheels
Other-than-serious$0$0Sep 27, 2010Final
Citation 1, item 9
29 CFR 1910.243(b)(2) · Guarding of portable powered tools
Other-than-serious$3,150$50Sep 27, 2010Final
Citation 1, item 11
29 CFR 1910.305(a)(2)(iv) · Electrical wiring methods
Serious$4,500$4,500Sep 27, 2010Final
Citation 1, item 12a
29 CFR 1910.1200(e)(1) · Hazard communication
Other-than-serious$4,500$50Sep 27, 2010Final
Citation 1, item 12b
29 CFR 1910.1200(h) · Hazard communication
Other-than-serious$0$0Sep 27, 2010Final
Citation 1, item 13
29 CFR 1926.20(b)(2) · Construction safety programs
Serious$6,300$6,300Sep 27, 2010Final
Citation 1, item 14
29 CFR 1926.95(a) · Criteria for personal protective equipment
Serious$4,500$4,400Sep 27, 2010Final

Inspection 300051968 OPENED APR 2, 1998Closed

Referral · Partial · Safety · 28 employees at the site · Closed Apr 2, 1998

90th & Maple, Omaha, NE 68134 · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

Inspection 116001538 OPENED DEC 27, 1995Closed

Complaint · Partial · Safety · 10 employees at the site · Closed Feb 15, 1996

30th & L, Omaha, NE 68102 · OSHA's record · Phone and website on Google Maps

Citation and ruleTypeProposedCurrentIssuedStatus
Citation 1, item 1
29 CFR 1926.652(a)(1) · Trench protection
Serious$800$480Jan 31, 1996Closed

Inspection 116001397 OPENED NOV 2, 1995Closed

Unprogrammed related · Partial · Safety · 2 employees at the site · Closed Feb 15, 1996

4508 South 28th Street, Omaha, NE 68107 · OSHA's record · Phone and website on Google Maps

No citations from this inspection.

The rules behind these citations

Current text from the Code of Federal Regulations. Some citations were issued under older wording.

29 CFR 1904.39 · Reporting deaths and severe injuries

29 CFR 1904.39(a)(2)

(2) Within twenty-four (24) hours after the in-patient hospitalization of one or more employees or an employee's amputation or an employee's loss of an eye, as a result of a work-related incident, you must report the in-patient hospitalization, amputation, or loss of an eye to OSHA.

29 CFR 1910.1200 · Hazard communication

29 CFR 1910.1200(e)(1)

(e) Written hazard communication program. (1) Employers shall develop, implement, and maintain at each workplace, a written hazard communication program which at least describes how the criteria specified in paragraphs (f), (g), and (h) of this section for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes the following:

29 CFR 1910.1200(h)

(h) Post-mortem data: Increased incidence and/or severity of post-mortem findings may be indicative of maternal toxicity. This can include gross or microscopic pathological findings or organ weight data, including absolute organ weight, organ-to-body weight ratio, or organ-to-brain weight ratio. When supported by findings of adverse histopathological effects in the affected organ(s), the observation of a significant change in the average weight of suspected target organ(s) of treated dams (mothers), compared to those in the control group, may be considered evidence of maternal toxicity.

29 CFR 1910.147 · Lockout/tagout

29 CFR 1910.212 · Machine guarding

29 CFR 1910.215 · Grinders and abrasive wheels

29 CFR 1910.22 · General requirements

29 CFR 1910.23 · Guarding floor and wall openings and holes

29 CFR 1910.243 · Guarding of portable powered tools

29 CFR 1910.305 · Electrical wiring methods

29 CFR 1926.20 · Construction safety programs

29 CFR 1926.652 · Trench protection

29 CFR 1926.95 · Criteria for personal protective equipment

Other poured concrete foundation and structure contractors employers in Nebraska

Alert subscribers get notified of each newly cited employer in Nebraska the morning it is posted. See the alert plans.

Source: U.S. Department of Labor, OSHA enforcement data. A citation is OSHA's allegation; employers can contest it, and the status column shows where each item stands. Something wrong on this page? Tell us.