Inspection 342592367 OPENED AUG 9, 2017Closed
1335 East 171st Street, Cleveland, OH 44110 · Fabricated Structural Metal Manufacturing · OSHA's record · Phone and website on Google Maps
Incident on Aug 1, 2017: Employee sustains amputation of thumb and ring finger when p
At 3:00 p.m. on August 1, 2017, Employee #1 was positioning a piece of sheet metal for bending. The employee's boot became caught in the cover of the foot pedal. The Cincinnati press brake was inadvertently activated, causing an amputation of his left thumb and ring finger. It was later determined that the foot pedal was defective.
| Citation and rule | Type | Proposed | Current | Issued | Status |
|---|---|---|---|---|---|
| Citation 1, item 1 OSH Act Section 5(a)(1) · General Duty Clause |
Serious | $3,623 | $3,500 | Nov 30, 2017 | Final |
| Citation 1, item 2 29 CFR 1910.110(e)(4)(iii) · Storage and handling of liquefied petroleum gases |
Serious | $2,897 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 3 29 CFR 1910.147(c)(1) · Lockout/tagout |
Serious | $2,897 | $2,000 | Nov 30, 2017 | Final |
| Citation 1, item 4 29 CFR 1910.157(g)(2) · Portable fire extinguishers |
Serious | $2,173 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 5 29 CFR 1910.178(l)(1)(i) · Forklifts and other powered industrial trucks |
Serious | $2,897 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 6 29 CFR 1910.179(j)(2)(iii) · Overhead and gantry cranes |
Serious | $2,897 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 7 29 CFR 1910.179(l)(3)(iii)(d) · Overhead and gantry cranes |
Serious | $2,897 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 8a 29 CFR 1910.212(a)(1) · Machine guarding |
Serious | $5,071 | $4,000 | Nov 30, 2017 | Final |
| Citation 1, item 8b 29 CFR 1910.212(a)(3)(ii) · Machine guarding |
Serious | $0 | $0 | Nov 30, 2017 | Final |
| Citation 1, item 9 29 CFR 1910.303(b)(7)(i) · Electrical equipment, general requirements |
Serious | $2,173 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 10 29 CFR 1910.303(g)(2)(i) · Electrical equipment, general requirements |
Serious | $2,897 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 11 29 CFR 1910.305(g)(2)(iii) · Electrical wiring methods |
Serious | $2,173 | $1,000 | Nov 30, 2017 | Final |
| Citation 1, item 12a 29 CFR 1910.1200(e)(1) · Hazard communication |
Serious | $2,173 | $500 | Nov 30, 2017 | Final |
| Citation 1, item 12b 29 CFR 1910.1200(h)(1) · Hazard communication |
Serious | $0 | $0 | Nov 30, 2017 | Final |
| Citation 1, item 12c 29 CFR 1910.1200(h)(3)(iv) · Hazard communication |
Serious | $0 | $0 | Nov 30, 2017 | Final |
| Citation 2, item 1 29 CFR 1903.19(d)(1) · Proving cited hazards were fixed |
Other-than-serious | $415 | $415 | Jul 23, 2018 | Final |